FISCHER Mess- und Regeltechnik GmbH
Start-up | 4
BA_EN_DE90
21
4 Start-up
NOTICE! If operated in explosive areas, the checks carried out in line with
the valid local regulations and guidelines for the installation and operation
of electrical systems in explosive areas must be carried out.
4.1 Installation control
Before starting the measuring device:
w
Check that the pressure lines are mounted correctly.
1. Is the measuring device undamaged?
2. Does the measuring device fulfil the requirements of the measuring point
specification?
3. Are the pressure lines mounted correctly?
4. Are the attachment screws tighten correctly?
5. Is the device adequately protected against precipitation and solar radi-
ation?
w
Check that all electrical supply and measuring lines are installed correctly.
1. Are the connection lines undamaged?
2. Do the cables used fulfil the requirements?
3. Is there strain relief on the mounted cables?
4. Are the connection plugs mounted correctly?
5. Is the ground connected correctly?
4.2 Switch on the measuring device
w
The measuring device can be switched on after a success installation con-
trol.
1. The start screen is now shown on the display.
1
2 3
4
DE90
1902981.03.977
v1.00
Fig. 25:
Start screen (2 channel)
Ê
After a successful start, the start screen switches to the measured value
display.
Summary of Contents for PRO-LINE DE90
Page 108: ...9 Attachments FISCHER Mess und Regeltechnik GmbH 108 BA_EN_DE90 Fig 141 CE_DE_DE90_ATEX ...
Page 113: ...FISCHER Mess und Regeltechnik GmbH BA_EN_DE90 113 Notes ...
Page 114: ...FISCHER Mess und Regeltechnik GmbH 114 BA_EN_DE90 ...
Page 115: ...FISCHER Mess und Regeltechnik GmbH BA_EN_DE90 115 ...