HotPort 5020-LNK node installation
15
•
Install all ground components in straight lines. If you must make a bend, do
not make a sharp bend.
•
Earth-to-ground should be less than or equal to 10 ohms.
•
Some salt compounds are corrosive and can cause copper ground rods to
corrode.
To prepare the soil for ground rods:
1.
If the soil contains rocks or sand, insert the ground rods into the ground.
2.
Pull out the ground rods.
3.
Put in an approved ground enhancement material into the holes where the
grounding rods go.
4.
Put in the ground rods.
Grounding a HotPort node
The certified installer is responsible for the calculation of the correct gauge of
the wire to be used to ground a mesh node. The antenna cables that come with
the HotPort 5020-LNK solution have integrated lightning arrestors.
Prerequisite: correct gauge of ground wire
Caution.
If the structure to which the node is attached is not properly
grounded, the node can be damaged by a power surge.
To ground a HotPort node:
1. Calculate the correct gauge of wire to be used in this procedure. Refer to the
National Electrical Code for grounding information.
Caution.
The certified installer is responsible for the correct calculation
of the wire gauge and other accessories that might be required to
ensure proper earth ground.
2.
a.
Cut three correct lengths of the correct gauge of wire.
b.
c.
Crimp the lug that holds with the wire for antenna connector 1.
d.
Crimp the lug that holds the wire from antenna connectors 1 and 2.
.
Crimp the lug that holds the wire from antenna connectors 2 and 3.
!
!
Summary of Contents for HotPort 5020-LNK
Page 1: ...HotPort FiretideInstallationGuide HotPort 5020 LNK Nodes Published March 2014 Revised 2016...
Page 8: ...HotPort5020point to pointsolution 2...
Page 16: ...Beforeyoupermanentlyinstall 10...
Page 32: ...HotPort 5020 LNK node installation 26...
Page 39: ...Troubleshooting 33 8 RemovetheEthernetcable...
Page 40: ...Troubleshooting 34...