AnF Enclosures
REV. 8-29-18 Page 7
While the panels are still upside-down, install the leveling legs. Locate the nutsert on the panels (See
Fig. 11). Take the leveling legs and screw them into the nutsert. The legs should be screwed in until
there is 1- inch of clearance between the top of the leg and the panel (See Fig. 16).
Fig. 16
Installing Leveling Legs Into Panels
After the leveling legs have been
installed, carefully fl ip the entire AnF
unit over so that it is resting on the
leveling legs.
NOTE:
If you have an ANF-74 or ANF-90, you will have 8 leveling legs to install.
Once the unit is turned over on the
leveling legs, make any adjustments to
the legs to make sure the unit is level.
This must be done on the installation
location.
Butt the inner fl ange of one of the panels to the non-fl ange side of another panel (See Fig. 13).
After the two ends are butt together, secure
them with self-tapping screws; one into the
inner hole at the top and one into inner hole at
the bottom of the two panels (See Fig. 15).
Before you completely tighten the screws,
check for squareness. Tighten screws.
Assemble the remaining sections the same
manner.
Fig. 14
Butting Ends Together
Fig. 15
Installing Self-Tapping Screws Into Panel
STEP 2
We strongly recommend
two people
when turning the AnF over.