Festo — CPX(-M)-FB33/34/35/43/44/45 — 2022-05f
Commissioning
15
Connection
Connecting hardware
Cover cap
CPX-FB33/43:
Network connection with M12 plug
Plug: NECU-M-S-D12G4-C2-ET
ISK-M12
CPX-M-FB34/44:
Network connection with RJ45 plug
Plug: FBD-RJ45-PP-GS
CPX-M-AK-C
CPX-M-FB35/45:
Network connection with SCRJ plug
Plug: FBD-SCRJ-PP-GS
Service interface
Connecting cable: KV-M12-M12-…
ISK-M12
Tab. 13: Examples of the connection technology and cover caps for degree of protection IP65/IP67
6.4
Power supply
Bus nodes are supplied with power via the interlinking blocks.
If there are problems with the power supply
7
Commissioning
7.1
Setting up PROFINET communication
NOTICE
Malfunction due to incorrect switch-on sequence.
• First switch on the operating voltage supply of all network stations and then the operating power
supply of the open-loop control.
CPX- M-FB34: cyclical process data exchange can freeze in exceptional cases in applications with
increased electrostatic load.
This results in an entry in the diagnostic memory with error number FN150.
• Restart to ensure normal operation.
• Reduce electrostatic charges in the vicinity of the product or use a CPX Terminal with metal inter-
linking.
1. Define the operating mode and diagnostic mode with the DIL switches of the bus node.
2. Set up the automation project for the higher-order controller using suitable software.
3. Import the device description file into the software
4. Configure the CPX Terminal in the software:
–
System structure
–
Network addressing
–
Address allocation of the modules
5. Transfer the automation project to the higher-order controller.