4.4 Reaction of the CP system to operating faults
If there is a fault on a CP module during operation, e.g.
due to cable fracture etc., the LED on the appropriate
string of the fieldbus node will light up. The status LED
on the relevant module will go out. All modules which
function faultlessly remain ready to operate.
You can now restore the defective connection during
operation, or replace the defective module without af-
fecting operation of the other modules in the other
strings. When the connection is restored or after re-
placement, the ready status of the relevant module will
be restored automatically.
4. Commissioning
CP... 9806A
4-11
Summary of Contents for Compact Performance System
Page 1: ...Compact Performance CP system Installation and commissioning...
Page 3: ...Part no 165 226 Title Manual Designation P BE CPSYS GB II CP 9806A...
Page 12: ...Chapter 1 System overview 1 System overview CP 9806A 1 1...
Page 33: ...1 System overview 1 22 CP 9806A...
Page 34: ...Chapter 2 Fitting 2 Fitting CP 9806A 2 1...
Page 46: ...Chapter 3 Installation 3 Installation CP 9806A 3 1...
Page 64: ...Chapter 4 Commissioning 4 Commissioning CP 9806A 4 1...
Page 82: ...Appendix A Technical appendix A Technical appendix CP 9806A A 1...