ATLAS D Ki 100 UNIT
18
GB
cod. 3540I690 - 02/2008 (Rev. 00)
Electrode - baffle position
After fitting the nozzle, check the electrodes and baffle are in the right positions, according to the distances shown be-
low. The distances should be checked after any work done on the head.
fig. 27 - Electrode - baffle position
3.2 Commissioning
B
Checks to be made at first lighting, and after all maintenance operations that involved disconnecting from the
systems or work on safety devices or parts of the boiler:
Before lighting the boiler
•
Open any on-off valves between the boiler and the systems.
•
Check the tightness of the fuel system.
•
Check the pre-filling of the expansion tank
•
Fill the water system and make sure that all air contained in the boiler and the system has been vented by opening
the air vent valve on the boiler and any vent valves on the system.
•
Make sure there are no water leaks in the system, hot water circuits, connections or boiler.
•
Make sure the electrical system is properly connected and the earth system works properly.
•
Make sure there are no flammable liquids or materials in the immediate vicinity of the boiler.
•
Fit the pressure gauge and the vacuum gauge on the pump (remove after starting) of the burner.
•
open the gate valves along the diesel pipe
Start-up
fig. 28 - Ignition
45.0°
6.5
3.5
3
1
L
VE
G
P
VE
G
P