Clamping and gluing process:
Once pad shoes, press arms and hydraulic cylinders have been positioned, the actual working
process can be started.
Equip the press with the glued work pieces so that they stand on the stop rail. Now pump the
hydraulic cylinders downwards until the desired pressing pressure is reached. Now place the side
pressure pipe in position. This is done by actuating the lifting mechanism and thus lifting the side
pressure pipe.
Make sure that the snap-in pins of the side pressure pipe snap into the rowes of holes above and
below, so that the resulting side load can be discharged optimally.
When gluing frames, ensure that the press shoes are seated at the corner points of
the frame so as to avoid deflection and possible damage to the workpiece.
Set up / Operation
Pump the hydraulic
cylinders downwards
Actuation of the lifting device,
move the side-pressure unit,
reduce the side-pressure unit
using the lifting device.