LAY OUT THE BUILDING SITE

After the site is prepared, lay out the building site.

Taking these steps 

before

 assembling the shelter saves 

time and ensures that the structure is positioned as

desired. 

Ground posts must be driven to the proper depth. Width

of the shelter is measured from the center of one

ground post to the center of the remaining ground post.

SQUARE THE SITE

Gather the parts:
•  Ground posts
•  5/16" x 2-1/2" machine bolts 
•  5/16" nuts
1.  Identify a corner where a ground post will be positioned 

and drive the first ground post into the ground.  

 

NOTE: 

Insert the ground post driver into the top of 

the ground post to protect the post and drive the post 

into the ground. 

The top of the post will be one (1) foot 

above the finished grade when properly driven.

 

 

4.  String a line at least as long as the building from the 

first stake at 90°. 

 

NOTE:

 A transit can be used to ensure an accurate 90°  

angle, or the 3-4-5 rule can be used. Refer to diagram.  

Using multiples of 3-4-5 such as 6-8-10 or 12-16-20  

helps to maintain an accurate 90° angle.

5.  After squaring the position of the building, measure the 

length and drive the next corner ground post.

6.  Repeat the same step for the last corner post. 

 

NOTE:

 The distance measured diagonally between 

corner posts must be equal for the building to be 

square.

7.  Check all dimensions (and adjust if needed) before 

driving the remaining posts to the required height.

8.  After all corner posts are accurately installed, tie a 

string line between the tops of the corner ground posts 

on the same side of the shelter. The string is used to 

identify the tops of all remaining ground posts. The 

string must remain tight and level.

9.  Use a tape measure to mark the 48" on-center 

locations of the remaining ground posts.

10. Drive the remaining ground posts into the ground at the 

required 48" on-center width and the height identified 

by the string. 

 

NOTE:

 Verify that the holes in the ground posts are in 

the proper position and that each post is plumb and 

driven to the correct depth. 

 

After the rafters have been assembled, the rafter ends 

are secured to the ground post using the upper hole.  

 

The bottom two (2) holes on the ground post are used 

for the optional baseboards.

11.  Continue with the 

Rafter Assembly

 steps that follow.

ATTENTION:

 Position the pre-drilled holes facing to the 

inside/outside of the shelter so they can be aligned with 

the bolt holes in the rafter legs. 

 

To align the bolt holes in the ground posts with those 

in the rafter 

after driving the ground posts,

 insert a 

tapered rod or pry bar into a ground post bolt hole and 

turn the post using the rod or pry bar.

2.  After the first corner ground post is in place, string a 

line the width of the building (center-to-center) and 

drive the second ground post into the ground just 

enough to hold it in place.

3.  Use a transit or line level to drive the second corner 

post to the same depth as the first ground post.

Outside of 

Shelter

Inside of 

Shelter

Ground 

Post

Summary of Contents for GrowSpan PB01700R4

Page 1: ...e 01 01 16 Photo may show a different but similar model STK DIMENSIONS PB01700R4 26 W x 12 H x 48 L PB01710R4 26 W x 12 H x 96 L 2016 Growers Supply All Rights Reserved Reproduction is prohibited with...

Page 2: ...t needed during the assembly process For safety reasons those who are not familiar with recognized construction methods and techniques must seek the help of a qualified contractor YOU MUST READ THIS D...

Page 3: ...ded with the shipment To aid in the assembly read through the following definitions before you begin to assemble your shelter Conduit An assembly of pipes used to secure the main cover and end panels...

Page 4: ...ot need to open the plastic bags containing smaller parts such as fasteners or washers if equipped SPECIAL NOTE Baseboards for Frame These instructions describe installing a baseboard recommended at g...

Page 5: ...photos will help you identify the different parts Some parts are not shown 102856 End Clamp 102548 Cross Connector Swaged Plain Swaged and Plain Rafter Sections CC6212 CC6213 Fabric Clips FA4482B Tek...

Page 6: ...Quick Start Guide Ground Level End Rafter Inside Rafter Roll Up Side Conduit Purlins Baseboards are supplied by customer Round Premium High Tunnels OVERVIEW This section describes assembling your high...

Page 7: ...re driving the remaining posts to the required height 8 After all corner posts are accurately installed tie a string line between the tops of the corner ground posts on the same side of the shelter Th...

Page 8: ...crews so they will not touch the cover once it is installed This is typically on the backside of the rafter which will be the surface visible from the inside of the high tunnel once the frame is assem...

Page 9: ...the purlin pipe in the joint where the rafter pipes are connected to keep purlins aligned during assembly 7 Repeat the previous step to install a second purlin section See the above diagram for detai...

Page 10: ...in to extend beyond the end of the end rafter Align with the center of the end rafter for best results If the purlin is too short to fit into the rafter end clamps without pulling the end rafter out o...

Page 11: ...rp edges on the frame and file them smooth so they will not cut the cover 2 Apply two layers of heavy duct tape on all pipe connections and clamps that may contact the cover ANCHOR THE ASSEMBLED FRAME...

Page 12: ...LLATION After the end panels are installed install the main cover The steps to install the main cover include 1 Attach poly latch U Channel 102197 along the high tunnel sides and tops of the high tunn...

Page 13: ...the cover into place Center cover side to side and end to end IMPORTANT To prevent damage to the main cover during installation additional personnel and lifts may be needed INSTALL POLY LATCH U CHANNE...

Page 14: ...irst end rafter until the entire length of the end of the main cover is secured in place 7 Stretch the cover to the other end of the building and repeat the steps to secure the main cover in the U Cha...

Page 15: ...of the Wrist assembly and attach it to the frame and the roll up side 4 Install the Anti Billow Rope system 5 Test the operation of the roll up side 4 Place the assembled conduit at the base of the si...

Page 16: ...ssembly will be located NOTE Verify that the lower end of the channel is slightly off the ground to allow it to move freely when the panel is rolled up and down 5 Secure the upper end of the channel b...

Page 17: ...m channel from the ground end This is the free end of the channel 13 Roll the cover conduit up to the Twist of the Wrist assembly 14 Attach the conduit to the square shaft of the assembly by inserting...

Page 18: ...nance information that follows NOTE If the poly latch U Channel was attached to a ribbon board as suggested the eyebolt can be mounted through the poly latch channel and ribbon board to the inside of...

Page 19: ...at anytime Remove debris and objects that may accumulate on the cover Use tools that will not damage the cover when removing debris Remove snow to prevent excess accumulation Use tools that will not...

Page 20: ...UND PREMIUM HIGH TUNNELS Revision date 01 01 16 QUICK START GUIDE 26 Wide Round Premium High Tunnels Frame shown may differ in length from actual frame 26 0 Width 12 6 15 16 Heigth FRONT Grid Represen...

Page 21: ...01 26R1602 End Clamp 102856 Mid Clamp 102548 End Clamp 102856 Mid Clamp 102548 End Clamp 102856 Mid Clamp 102548 End Clamp 102856 Mid Clamp 102548 End Clamp 102856 Mid Clamp 102548 ATTENTION Except fo...

Page 22: ...PREMIUM HIGH TUNNELS Revision date 01 01 16 7 131S075 1 131P0735 Purlin Run 48 0 Length Customer Supplied Baseboard Customer Supplied Ribbon Board 4 0 on center Rafter Spacing center to center SIDE P...

Page 23: ...PREMIUM HIGH TUNNELS Revision date 01 01 16 96 0 Length 15 131S075 1 131P0735 Purlin Run Customer Supplied Baseboard Customer Supplied Ribbon Boards 4 0 on center Rafter Spacing center to center SIDE...

Page 24: ...id Rafter P urlin Connection View 2 Rafter 102856 View 1 End Rafter Purlin Connection Purlin 102548 Rafter View 2 Mid Rafter Purlin Connection Purlin ATTENTION Install a Tek screw through each clamp i...

Page 25: ...25 GROWSPAN ROUND PREMIUM HIGH TUNNELS Revision date 01 01 16 Space below is reserved for customer notes...

Reviews: