To install belt pulley and V-belt follow the procedures below:
①
Check each V-belt for any pollutions by grease or dirt;
②
Keep V-belt in a proper tension: When V-belt is too loose, it tends to slippage. On the other hand,
if it is too tight, it leans to a great tensile force to the shaft, which will decrease its service life.
③
To check the tension of the belt at the center of the tangent line of the two belt pulleys, namely at
L/2. Exert a force of190N at the midpoint of the belt, enabling its deflection offset to be 16mm as
proper tension.
④
Check the coplanarity of the two pulleys for offset within 1mm, or else adjustment is required.
4.3 Electric installation
(1) Electric connection
①
Please refer to Fig.4-13 for electric control diagram to connect the electric cables to
the central control room.
②
Properly protect the cable channels in central control room.
④
Keep the central control room clean and free of dust. See Fig.4-13.
Fig.4-13 Layout of electric connection
(2)Schematic diagrams of electric control
Main control room