Guidelines for AC-powered equipment
An AC-powered installation must meet the following requirements:
•
Install the unit using a 20 amp external branch circuit protection device.
•
Normally, one power feed is used for each individual power supply.
Caution: Risk of explosion if battery is replaced by an incorrect type. Dispose of used batteries
according to the instructions.
Attention: Il y a risque d'explosion si la batterie est remplacée par une batterie de type incorrect.
Mettre au rebut les batteries usagées conformément aux instructions.
Important: The platform must be installed in a RESTRICTED ACCESS LOCATION such as a central
office or customer premises environment.
Note: The following guidelines apply to STATIONARY PLUGGABLE EQUIPMENT TYPE A with
simultaneous multiple connections to the AC MAINS SUPPLY:
•
The building installation shall provide a means for connection to protective earth; and
•
The building installation shall provide a means for connection to protective earth; and
•
A SERVICE PERSON shall check whether or not the socket-outlet from which the equipment is to
be powered provides a connection to the building protective earth. If not, the SERVICE PERSON
shall arrange for the installation of a PROTECTIVE EARTHING CONDUCTOR from the separate
protective earthing terminal to the protective earth wire in the building.
Note: High leakage current. Earth connection essential before connecting supply.
41
Platform Guide: 8950
Summary of Contents for BIG-IP 8950
Page 1: ...Platform Guide 8950 MAN 0320 03 ...
Page 2: ......
Page 38: ...38 Platform Maintenance ...
Page 50: ...50 Platform Specifications ...
Page 51: ...Appendix D China RoHS Requirements Topics Hazardous Substance Levels for China ...
Page 56: ...56 Index ...