LEDs and Buttons
ARX®4000 Hardware Installation Guide
4 - 11
The power supplies in the control plane and data plane differ in appearance
and in LEDs. The power supplies in the control plane have 1 LED. The
following table lists and describes the states indicated by this LED.
The power supplies in the data plane have 3 LEDs. The following table lists
and describes the states indicated by these LEDs.
Ethernet-Port Link Status LEDs
The Ethernet ports on the front of the ARX (data plane) have two LEDs, one
in the upper left corner and one in the upper right corner:
• Upper left. Activity LED. Blinking yellow indicates packet traffic.
• Upper right. Link-status LED. Steady green indicates that the port is
enabled and a link is established.
Ethernet Management Port LEDs
The Ethernet Management port provides two LEDs located on the network
interface connector. The link/activity LED (to the right of the connector)
indicates network connection when on, and transmit/receive activity when
blinking. The speed LED (to the left of the connector) indicates 1000-Mbps
operation when amber, 100-Mbps operation when green, and 10-Mbps when
off.
Table 4.4
Control Plane Power Supply LED States
Description of State
Continuous green. AC is present and the component is powered on.
Blinking green. AC is present but the component is powered down.
Amber. AC is not present.
Off. No AC; no power.
Table 4.5
Power Supply LEDs and States
LED
Description of State
Top
Green. Power on.
Off. No power.
Middle
Amber. Power supply has faulted.
Off. Power supply is “Good.”
Bottom
Green. AC present.
Off. AC not present.
Summary of Contents for ARX-4000
Page 1: ...ARX 4000 Hardware Installation Guide version 4 00 001 810 0055 00 ...
Page 2: ......
Page 5: ...Table of Contents ...
Page 6: ......
Page 9: ......
Page 10: ...Table of Contents x ...
Page 12: ......
Page 22: ......
Page 28: ...Chapter 2 Product Overview 2 8 ...
Page 30: ......
Page 38: ......
Page 50: ......
Page 56: ...Chapter 5 Unpacking and Installing the Switch 5 8 ...
Page 58: ......
Page 70: ...Chapter 6 Connecting the Switch to the Network 6 14 ...
Page 72: ......
Page 76: ...Chapter 7 Operational Status and Troubleshooting 7 6 ...
Page 78: ......
Page 90: ...Appendix A Removing and Replacing FRUs A 14 ...
Page 91: ...Index ...
Page 92: ......