Before rigging make sure that the installation area can hold a minimum point load of 10 times the
installation's weight.
For suspending crossbeams, Alu-Bars, etc. always use a minimum of two hooks.
Attach the upper fixation of a C-hook to the crossbeam and tighten the fixation screw. Attach the Alubar to
the lower fixation of a C-hook and tighten the fixation screw.
At the suspended part, always install a safety-rope that can hold at least 12 times the weight of the
installation. You must only use safety-ropes with quick link with screw cap. Pull the safety-rope through the
attachment eyelet and over the trussing system or a safe fixation spot. Insert the end in the quick link and
tighten the safety screw.
The trussing system must always be earthed!
DANGER TO LIFE!
Before taking into operation for the first time, the installation has to be approved by an expert!
5.3 Connections
5.3.1 Connection with the mains
Connect the device to the mains with the industrial plug.
The occupation of the connection-cables is as follows:
5.3.2 Outputs
Output is via 6 safety sockets.
Connect your loads via the output-sockets. The maximum load per channel is 3,680 W (resistive). Please
note that the maximum current must never be exceeded.
6. OPERATION
The AB-616X Alubar is a holding device. Please control the individual spotlights via your controller.
7. CLEANING AND MAINTENANCE
The operator has to make sure that safety-relating and machine-technical installations are inspected by an
expert after every four years in the course of an acceptance test.
The operator has to make sure that safety-relating and machine-technical installations are inspected by a
skilled person once a year.
The following points have to be considered during the inspection:
1) All screws used for installing the devices or parts of the device have to be tighly connected and must not
be corroded.
2) There must not be any deformations on housings, fixations and installation spots (ceiling, suspension,