Installation
Filling the heating system
53
Installing the pellet hoses on the pellet hopper
On the ends of both pellet hoses, free around 10 cm of
the copper wire strands from the hoses.
Fig. 9-50: Exposed copper wire strands
Push the two pellet hoses onto the connections and
secure them with hose clamps.
Fig. 9-51: Connections on the pellet bin
Connect the copper wire strands from both pellet
hoses to the yellow-green earthing cable (next to the
connections).
Fig. 9-52: Connecting the copper wire strands to the earth
Mounting the pellet hoses on the discharge
On the ends of both pellet hoses, free around 5 cm of
the copper wire strands from the hoses. Bend the
copper wire strand inside the pellet hose.
Fig. 9-53: Copper wire strands
Push the two pellet hoses onto the connections and
secure them with hose clamps.
9.12
Filling the heating system
Filling the heating system
Fill the heating system with softened water, refer to
chapter
.
Summary of Contents for ePE-K 140
Page 1: ...2020 07 21 EN 0000000451 V 008 5303 00 939074 003 Pellet boiler ePE K 140 170 kW Installation ...
Page 55: ...Installation Network connection 55 ...
Page 61: ...Electrical connections Overview of circuit boards 61 ...
Page 65: ...Electrical connections Circuit board HA C5 65 ...
Page 82: ...www eta co at ...
Page 83: ......
Page 84: ...www eta co at www eta co at downloads DOWNLOAD ...