General
Warranty, guarantee and liability
5
1.3
Warranty, guarantee and liability
Requirements
We can only accept liability for the function of our
products if they are correctly installed and operated.
This is only possible if the conditions below are
complied with.
Maximum of 2,000 hours at full load per year
The boiler described in this user manual may only be
used for heating and producing hot water, with no more
than 2,000 full-load hours annually.
Installation in a dry room
For set-up, a dry room is required. In particular, only
condensation dryers may be used as clothes dryers in
the same room.
Observe local building and fire safety regulations
Local building and fire safety regulations must be
observed.
Suitable fuel – logs
The log boiler is suitable for use with wood briquettes
and air-dried split logs with no more than 20% water
content. Use with unsuitable fuels, especially refuse,
coal and coke, and also wet wood, is not permitted.
Suitable fuel
The boiler is suitable for use with wood pellets
according to EN ISO 17225-2:2014, quality class A1,
ENplus-A1. Operation with unsuitable fuels, in
particular those containing halogens (chlorine) or high-
slag pellets such as from grain waste, is not permitted.
Ensure supply air is free from aggressive
substances
The air supplied to the boiler must be free from
aggressive substances such as chlorine and fluorine
from solvents, cleaning agents, adhesives and propel-
lants, or ammonia from cleaning agents, to prevent
corrosion of the boiler and chimney.
pH value between 8 and 9
The pH value of water used to fill the heating system
must be between 8 and 9.
Use a sufficient number of shut-off valves
Set enough shut-off valves to avoid bleeding large
amounts of water during repairs. Any leaks in the
system must be repaired at once.
Minimum return temperature 60°C
Ensure a minimum return temperature of 60°C to the
boiler.
Install safety valve and thermal relief valve
A safety valve (triggered at 3 bar) as protection against
excess pressure and a thermal relief valve (triggered
at 97 °C) to protect against overheating must be
installed by the contractor.
Provide a sufficiently large expansion tank or a
pressure maintaining device
To prevent air from being drawn in while the system is
cooling, the heating system professional must provide
a sufficiently large expansion tank or a pressure
maintaining device.
Open expansion tanks must not be used.
Sufficient power
Operation at lower power than the lowest power
specified on the type plate is not permitted.
Expanding the control system
Only components provided by us may be used for
expanding the control system, unless these are
generally available standard devices, such as thermo-
stats.
Regularly perform cleaning and maintenance
Cleaning and maintaining the product is essential. The
required steps and intervals are either contained in this
documentation or included as a separate document.
Repairs
Repairs are only permitted using spare parts provided
by us. The only exceptions are common standardised
parts such as electrical fuses or fastening materials, as
long as they possess the required features and do not
restrict the functionality of the system.
Proper installation
The installing contractor is liable for proper installation
according to the corresponding installation instructions
and the relevant rules and safety regulations. If you as
customer have installed the heating system partly or
entirely without relevant training and in particular
without up-to-date practical experience, without having
the installation checked by a trained and responsible
expert, we exclude defects in our delivery and conse-
quential damages resulting from this cause from our
warranty, guarantee and liability.