Estun E200PS Operation Manual Download Page 13

 

E200PS Operation Manual 

 

11 

 

3.4 Multi-Step 

 

In the actual processing, operator user pedal switch to control the shearing 

process. In 

PROGRAM

 page, you can finish the complex operation with carefully 

programmed. 

 

Step 1 

When the E200PS device is electrified, wait a few seconds into the 

SINGLE

 page 

(Default page). 

Step 2 

Press 

  to enter the 

PROGRAMS

 page, as shown in Figure 3-3. 

[Operation Guide]

 

-

 

Program-Number is used for storing Multi-Step programming, in order to work again. 

E200PS CNC device provide 40 Program-Number to user. 

-

 

Press 

  to select the target Program-Number and press 

 

to enter, and then the editorial content is automatically saved in this program. 

PROGRAMS

0 P

      : 1program

      1 ST

1

2

5

3

4

11

12

15

13

14

6

7

10

8

9

16

17

20

18

19

 

Figure 3-3 

The 

PROGRAMS

 page 

 

Step 3 

Select the target Program-Number, such as 

2program

 and press 

  to enter 

PROGRAM

 page, as shown in Figure 3-4. 

[Operation Guide]

:

 

Press 

  to select the parameter you want to modify, 

input the value and press 

  to finish the operation. 

 NO.

2

   

PROGRAM

      :Total Step

 

X=

   10.00   G =

1.00

    ST:

           3 STEP

    PP:

         50 PIECE

    CP:

         50 PIECE

 

Figure 3-4 

The 

PROGRAM

 page 

 

Summary of Contents for E200PS

Page 1: ...E200PS Operation Manual Version V1 02...

Page 2: ...2 2 Multi Step 6 2 2 1 Background 6 2 2 2 Analysis 6 2 2 3 Procedure 6 Chapter 3 Operation Description 8 3 1 Tipwizard 8 3 1 1 Start and Stop 8 3 1 2 Parameter Setting 8 3 1 3 Alarm Reset 8 3 1 4 Moni...

Page 3: ...ystem Operator use the machine to do the programming work set the programming constant parameters Attention Copy right is preserved by ESTUN It is not allowed to add or delete part or all of the manua...

Page 4: ...fully and adhere them strictly Risk of injury If you do not adhere the safety advise adjoining this symbol there is danger to life and health of individuals Hazard to individuals If you do not adhere...

Page 5: ...precision and reduce screw clearance The action CUT and EOS is controllable Pneumatic feeding causes to convey the material to be nimble Backgauge can automatic homing Backgauge can be adjusted throu...

Page 6: ...nt key in case of manual adjustment make adjustment object move in forward direction at low speed Manual movement key in case of manual adjustment make adjustment object move in backward direction at...

Page 7: ...rameter Setting XP 100 00mm GP 1 00mm DX 5 00mm CL 80 PP 10 Others According to the actual situation to set 2 1 3 Procedure Step 1 When the E200PS device is electrified wait a few seconds into the SIN...

Page 8: ...ill edit and save in the 2program set the following parameters on the PROGRAM page Page Parameter Setting PROGRAM ST 3 PP 5 1 3ST XP 100 00mm GP 1 00mm DX 5 00mm Repeat Times 1 2 3ST XP 300 00mm GP 1...

Page 9: ...ccording to Step4 the result of modifying is as shown in Figure 2 3 PROGRAM2 1 3ST DestPos Of Axis X X 10 00 G 1 00 XP 100 00 mm GP 1 00 mm DX 5 00 mm Cut Length 80 Repeat Times 1 TIMES Figure 2 3 Ste...

Page 10: ...er Setting When editing the parameter press to select the parameter you want to modify input the value and press to finish When editing the parameter please accord to the tip on the page to edit If th...

Page 11: ...ngle Run Programs Mutil Step Mutil Step Run CONST System Parameter DIAGNOSE IO MONITOR ALARM RECORD Password 14789 Password 5656 P Press Press l Press l Press Press Press Press Press Press Press Press...

Page 12: ...o RUN page Press to stop the machine the page on the device enters to SINGLE page SINGLE DestPos Of Axis X Unit mm X 100 50 G 1 05 XP 55 00 GP 0 00 DX 0 00 CL 80 PP 0 CP 0 XP 55 00 Figure 3 2 The SING...

Page 13: ...in order to work again E200PS CNC device provide 40 Program Number to user Press to select the target Program Number and press to enter and then the editorial content is automatically saved in this pr...

Page 14: ...ST on the PROGRAM page Please pay attention the sequence of the step e g 1 3ST 1 indicates the current step 3 indicates the total step The machine will run in sequence Press to enter each step page f...

Page 15: ...ANUAL page to do relevant operation When the E200PS device is electrified wait a few seconds into the SINGLE page Default page press or enter MANUAL page as shown in Figure 3 6 Operation Guide Move th...

Page 16: ...13 14 15 16 17 18 19 20 AI IO 01 02 03 04 05 06 07 08 09 10 INPUT 11 12 13 14 15 16 17 18 19 20 01 02 03 04 05 06 07 08 09 10 OUTPUT 11 12 13 14 15 16 17 18 19 20 IO MONITOR INPUTS INPUT OUTPUTS OUTPU...

Page 17: ...en the device is in multi step programming the program can t change step Check U_Limit and EOS terminals are connected to 24V or not When the device is in multi step programming the program can t coun...

Page 18: ...eed The current position of X axis is out of the soft limit range it is necessary to move the X axis to the soft limit range manually A 11 Slider Block err The slider is not on the TDC in the case of...

Page 19: ...G axis is enabling the operator assigns to the G axis of a correct value to represent current size of the gap SINGLE XP 0 00 9999 999 999 9 999 mm inch Program position of X axle GP 0 00 0 99 99 mm in...

Page 20: ...ue is the remain work piece STEP XP 0 00 9999 999 999 9 999 mm inch Program position of X axis GP 0 00 0 99 99 mm inch Program position of G axis DX 0 00 0 9999 999 mm inch Retract distance of X axle...

Page 21: ......

Reviews: