Instalacion_93 v04
.fm - 13/6/18
SKY electromechanical operator
23
INSTALLATION
7
FINAL CHECKS
Closing thrust check
Installation must respect the values indicated
in Standard EN 12453:2000. All measurements
must be made in line with the method
described in Standard EN 12445:2000.
• F
d
< 400N in spaces between 50mm and 500mm
• F
d
< 1400N in spaces > 500mm
User instruction
1
Instruct the user with regards to the use and
maintenance of the installation and provide him/her
with the user manual.
2
Signpost the door, showing that it opens
automatically and indicating how to operate it
manually. Where appropriate, indicate that
operation is using the remote control.
G1
G2
G3
6
7
P93W
ST1
FT1
P1 P2 P3
ST2
FT2
P4 P5 P6
STOP
P7 P8
P11 P12
LOCK
FCA1
FCC1
P15 P14 P16
P22 P23
Courtesy
Light
Lamp.
G7 G8
G9 G10
24Vac
N
L
POWER
MOTOR1 (G2-G1-COM)
3
Operator parts (SK130, SK135):
D:
Unlock switch
K:
Thermal protector
FCA:
Opening limit switch
FCC:
Closing limit switch
FCS:
Additional limit switch (to be used in
accordance with the requirements of the
customer or installation)
Control board parts (VIVO-T101):
PUL1:
Open mini-pushbutton
PUL2:
Close mini-pushbutton
SW1:
Main switch
SW2:
DIP switch programming
Operator connections SK130, SK135:
1
Opening limit switch (FCA)
2
Limit switches common
3
Closing limit switch (FCC)
4-5
Additional limit switch (FCS)
6-7
Thermal protector / unlock switch
U, V, W:
Motor connections
PE:
Earth connection
Press PUL1 (open) and PUL2 (close) to check that
the turning direction of the operator is correct. If
it is not, interchange connections V and W.
VIVO-T101
SK130-SK135
THREE PHASE OPERATORS (SK130E, SK135E, SK130C and SK135C)
with VIVO-T101 board