3
Preparation of first initial operation
Before commissioning the lifting system, the entire system must be assembled correctly according to the as-
sembly instruction. Commissioning is prohibited until the entire system complies with the provisions of EG
Machinery Directives 2006/42/EG. For this, a risk analysis of the complete system must be carried out so
that you can react to possible residual dangers (for example by constructive measures or by instructions in
the operating instructions and/or by safety instructions on the system.)
3.1
Mounting the control box and connecting the cables
Mounting of the control box underneath a table top:
ATTENTION
During mounting of the control box the power cable needs to be disconnected from the
mains!
1.
Place the control box to the desired location and mark the drill holes with a pen.
2.
Pre-drill two holes (Ø 3 mm).
Be careful not to drill through the table top!
3.
The control box is mounted with two screws (cap screws DIN7981C 4.8xL, cap-Ø 9.5 mm).
NOTE
When tightening the screws do not exceed a maximum torque of 2 Nm!
NOTE
The motor cable has got a length of
1’
750 mm. If needed, up to 5 motor extension cables
can be con
nected. They have a length of 1’200 m
m.
124.00137: PXD compact motor extension c
able 1’200 m
m
NOTE
The cable of the
manual control switch has got a length of 1’800 m
m, and if needed it can
be expanded with up to 3 extension
cables. They have a length of 1’000 m
m.
124.00071: PXD manual control switch extension cable
1’000 m