First initiation
Warning!
At the first initiation through inexperienced personnel you endanger the
personnel and property values. We do not assume accountability for defects that
were caused by an incorrect use, f. e. by inexperienced personnel.
3.5.1 Cleaning
Clean up all parts that were supplied with anticorrosion agent for
storage and transport with petroleum
The use of dissolvers, diluents for cell lacquer or other cleanser
agents that may attack the lacquer are improper.
Observe therefore the information of the cleanser agent manufacturer
Oil all bare machine parts; use therefore an acid
– free lubricant
Lubricate all movable parts
3.5.2 Sight check/ manual function check
Attenntion!
Machine may not be connected with grid!
Remove all transport lockings
Check whether the machine has visible defects
Check all mechanic components about smoothness
Check all control elements about mechanic function and smoothness
3.5.3 Electrical connection
The mains plug is correct pre
– assembled at the front side.
Check whether the circuit is accordant to the information of the
machine connection data.
3.5.4 Function check
Accomplish a safety check at the machine (view safety check at the
machine)
Let the machine run empty for one hour
Check the machine about bizarre sounds in both running directions
Check the temperature of the motor and the roller bearings
Let the machine run under load and check again about sound and
temperature