15
Follow the steps below respectively to make electrical connections of your product.
1.
For the product to operate properly, insert the three phase, one neutral cable and
current cables of the three phases into the relevant inputs on the product.
2.
Make the step connections as described in the connection diagram. Make sure that you
connect a three-phase capacitor to the reference step here.
3.
You can connect shunt reactors to any step except for the reference step.
4.
Make the communication connections.
5.
Establish the alarm outlet connections.
6.
Insert the battery included in the package.
7.
Check the connections above and make sure that they are correct. Never energize the
product before checking.
8.
Connect power supply to Aux input.
1.10 Start-up the RGP Product
Follow the steps below respectively to start-up the product.
1. Once your product is energized, you will see the Language Selection, Tutorial Mode and Auto
Setup menus respectively and you will be prompted to set the relevant parameters.
2. The product will run the automatic connection scanning function. Phase currents must have a
value other than zero for the product automatically detect the connection error. The product will
switch on and off the reference step when correcting the connection error (phase sequence error and
current transformers polarity error).
3. If the rapidly changes in loads and the non-linear (Thyristor Triac Controlled, with Frequency
Converter, UPS etc.) loads are too much, the product might not be able to automatically correct
the connection. In this case, switching off this type of loads temporarily, and then de-energize and
energize the product and repeat the process.
4. Once the connection has been corrected, the product will run the automatic step detection
function. It switch on and off the steps one by one to detect their power and connection types.
5. You can connect desired number of capacitor and/or reactors to the steps of the RGP product
(except for the reference step), as long as they are three-phase, and mono phase
6. Once the Step recognition is complete, the product will run the automatic (SVC) recognition
function.
7. Your product will operate with factory settings during the first use.
Supply voltage is connected separately, Aux Supply, Voltage and Current Measurement
inputs are connected to ensure three-phase-neutral. The product will not operate without a
three-phase connection.
!
1.10 Start-up the RGP Product