Introduction 

Audience 

This manual is intended for use by anyone required to install and operate this battery.  Be sure 
to review this manual carefully to identify any potential safety risks before proceeding.  The 
owner must be familiar with all the features and functions of this battery before proceeding.  
Failure to install or use this battery as instructed in this manual can result in damage to the 
battery that may not be covered under the limited warranty. 

EnergyCell 1000XLC 

The EnergyCell 1000XLC is a high-performance Valve Regulated Lead-Acid (VRLA) battery 
designed for long life, fast installation, and low maintenance.  Featuring a carbon additive that 
reduces sulfation on the negative plate, the 1000XLC has exceptional cycle life and a 10-year 
warranty, combining the benefits of proven lead acid technology with advanced chemistry.   
The 1000XLC is also designed for safety with minimal offgassing under normal charging 
conditions and leak-proof engineering.  These attributes and more make the 1000XLC an 
excellent candidate for storing residential or light commercial renewable energy.

   

 

 

 

Figure 1 

EnergyCell 1000XLC 

 

 

 

 

Flame 

Arresting 

Safety 

Vent

 

 

Terminal 

19½

"

 (49.7cm) 

11

15

/

16

"

 

(30.3 cm)

 

"

  

(17.2 cm)

 

Summary of Contents for Outback Power EnergyCell 1000XLC

Page 1: ...EnergyCell 1000XLC Owner s Manual...

Page 2: ...ATION PROVIDED IN ITS MANUALS OR OTHER DOCUMENTATION b ASSUMES NO RESPONSIBILITY OR LIABILITY FOR LOSS OR DAMAGE WHETHER DIRECT INDIRECT CONSEQUENTIAL OR INCIDENTAL WHICH MIGHT ARISE OUT OF THE USE OF...

Page 3: ...Storing EnergyCell 1000XLC Batteries 8 Capacity 8 State of Charge 8 Installation 11 Battery Installation 11 Pre Installation Check 12 Installation Procedure 13 Operation 25 Commissioning 25 Charging...

Page 4: ...near the batteries Always use insulated tools Avoid dropping tools onto batteries or other electrical parts Keep plenty of fresh water and soap nearby in case battery acid contacts skin clothing or e...

Page 5: ...nergyCell 1000XLC is a high performance Valve Regulated Lead Acid VRLA battery designed for long life fast installation and low maintenance Featuring a carbon additive that reduces sulfation on the ne...

Page 6: ...0XLC Assembly IMPORTANT The surface supporting the assembled cabinet must be designed to support 27 3 psi 1 92 kg cm2 Concrete is ideal Total weight of cabinet assembly with batteries is 4 574 lb 2 07...

Page 7: ...d o Bus bars and safety covers included o Dielectric grease included o Grounding Wire o Cables CAUTION Fire Hazard Install properly sized battery cabling and interconnect cables The cable ampacity mus...

Page 8: ...he duration of current flow A draw of X amperes for Y hours equals an accumulation of XY amp hours Because the battery s chemical reaction constantly releases energy its amp hour capacity is affected...

Page 9: ...ow as 50 depth of discharge DoD This is common in a cycling application such as an off grid system However for optimal life the best practice is to avoid ever discharging below 50 Lower DoD levels can...

Page 10: ...Introduction 10 900 0258 01 00 Rev A This page intentionally left blank...

Page 11: ...iew the physical state of the battery as required o The battery should be installed with a minimum 36 91 4 cm clearance in front This allows access for testing maintenance and any other reasons Batter...

Page 12: ...tallation Check Inspect batteries carefully for any physical damage or leaking and check safety vents Ensure all batteries in each module are oriented consistently with positive terminals on one side...

Page 13: ...et of 2 bars closest to the positive battery terminals should be installed adjacent to each other while the bars closest to the negative terminals should be installed with their outer ends flush with...

Page 14: ...olts and M3 screws note that beams fasten onto the same side of the module frame as the gapped support bars installed previously which is also the side closest to the negative terminals On module 1 on...

Page 15: ...mounting holes on the floor and drill a 9 16 14 mm diameter hole 2 70 mm deep in each of the four positions Clean any dust or debris from the holes b Position module 1 so the holes in the metal tabs a...

Page 16: ...e is available remove the batteries from the module one by one 200 lb 90 kg stack the empty module and then insert the batteries Then repeat with module 3 above module 2 Make sure to follow the altern...

Page 17: ...ith M3 screws near the center of the top front of module 4 frame in the gap between the two support bars installed earlier Install cover on top of module 4 Then install 4 module on top of module 3 Fig...

Page 18: ...en rows If correct the support bars attached to front of modules should be matched with the center gap between support bars showing where module 2 meets module 3 and the support bars adjacent to each...

Page 19: ...electric grease such as NO OX ID or NCP 2 Carefully install short bus bars using M10 bolts so that batteries are connected in series Torque bolts to 28 1 to 33 8 N m 287 to 344 kgf cm or 531 Lbf in th...

Page 20: ...and B are secured with M10 bolts while bus bars C and D are secured with M8 bolts Torque M10 bolts to 17 2 2 5 N m 175 25 kgf cm and M8 bolts to 6 2 N m 63 2 kgf cm Figure 13 Install Long Bus Bars and...

Page 21: ...Installation 900 0258 01 00 Rev A 21 10 Install side shields using M3 screws Begin at the back then proceed to the front and lastly both sides Figure 14 Install Long Side Panels M3 Screws 16 per side...

Page 22: ...Installation 22 900 0258 01 00 Rev A 11 Install front cover 4 separate panels Figure 15 Install Front Cover Panels M3 Screws M3 Screws M3 Screws...

Page 23: ...battery cables to the top bus bars using M12 bolts Install the Equipment Grounding Conductor to the screw provided near the lower rear corner of the side panel Figure 16 Install Battery Cables M12 Bo...

Page 24: ...0258 01 00 Rev A 13 Install the bus bar cover on top by locking into place with side tabs and securing with two M3 screws on back side of cover Figure 17 Install Bus Bar Terminal Cover M3 Screws back...

Page 25: ...lk stage is a constant current stage The charge current is maintained at a constant high level not to exceed 200 Adc per battery until the voltage reaches 58 Vdc 2 42 Vpc At the end of the bulk stage...

Page 26: ...ing and data recording The programming may be use with the following settings Amp Hours 958 Ah Charge Time 1 minute Charge efficiency 100 Return Amps 19 2 Adc Charge voltage 57 6 Vdc Temperature Compe...

Page 27: ...g any EnergyCell battery Excessive voltage could result in battery damage which is not covered under the EnergyCell warranty For any EnergyCell battery if the charger settings are too high this will c...

Page 28: ...Operation 28 900 0258 01 00 Rev A NOTES...

Page 29: ...abuse Replace battery as necessary Heat damage or melted grease at terminals Loose or dirty cable connections Check and clean all connections Physical damage on terminals may require the battery to b...

Page 30: ...leakage of electrolyte o Any evidence of corrosion at cell terminals connectors or racks o Ambient temperature and condition of ventilation equipment o Current and voltage during charge cycle Measure...

Page 31: ...258 01 00 Rev A 31 Cell Voltage Records Date Date Date Cell 1 Cell 2 Cell 3 Cell 4 Cell 5 Cell 6 Cell 7 Cell 8 Cell 9 Cell 10 Cell 11 Cell 12 Cell 13 Cell 14 Cell 15 Cell 16 Cell 17 Cell 18 Cell 19 Ce...

Page 32: ...Troubleshooting and Maintenance 32 900 0258 01 00 Rev A NOTES...

Page 33: ...e Charge Voltage 58 Vdc Maximum Charge Current 200 Adc Recommended Charge Current 168 Acd Charging Temperature Compensation Factor 5 mV C cell Relative Humidity 0 to 95 non condensing Terminal M10 bol...

Page 34: ...4 Weight and Volume of Battery Components Battery Type Battery Weight Electrolyte Weight Electrolyte Volume H2SO4 Weight Lead Weight kg lb kg lb ml gal kg lb kg lb EnergyCell 1000XLC 73 8 162 73 16 8...

Page 35: ...EnergyCell Batteries 900 0258 01 00 Rev A 35 This page intentionally left blank...

Page 36: ...Masters of the Off Grid First Choice for the New Grid 17825 59th Avenue N E Suite B Arlington WA 98223 USA...

Reviews: