Commissioning
8.1
Post-installation check
Before commissioning the measuring point make sure that all final checks have been
carried out:
• "Post-mounting check" checklist → 17
• "Post-connection check" checklist→ 22
8.2
Switching on the transmitter
Once you have completed the post-connection checks, switch on the supply voltage. The
transmitter performs a number of internal test functions after power-up. During this
process, the following sequence of messages appears on the display:
Step Display
1
"Display" text and firmware version of the display
2
Device name with firmware version, hardware version and device revision
3
Displays the sensor configuration (sensor type and type of connection) along with the configured
measuring range
4a
Current measured value or
4b
Current status message
If the switch-on procedure is not successful, the relevant diagnostic event, depending on the cause,
is displayed. A detailed list of diagnostic events and the corresponding troubleshooting instructions
can be found in the "Diagnostics and troubleshooting" section → 37.
The device works after approx. 7 seconds, including the attached display. Normal
measuring mode commences as soon as the switch-on procedure is completed. Measured
values and status values appear on the display.
If the display is attached when the Bluetooth interface is activated, display
initialization is performed twice and Bluetooth communication is disabled
simultaneously.
8.3
Configuring the measuring device
Wizards
The starting point for device wizards is in the
Guidance
menu. Wizards not only query
individual parameters but also guide the user through the configuration and/or
verification of entire sets of parameters with step-by-step instructions, including
questions, that are comprehensible for the user. The "Start" button can be disabled for
wizards that require specific access authorization (lock symbol appears on the screen).