Upstream cone removal
Figure 9-6:
7.
Remove the upstream hanger assembly from the opposite end.
a. To do this you must insert a pin into the hole in the upstream hanger hub.
b. Insert the shaft from the downstream end and push the shaft against the pin.
c. Tap the shaft lightly to free the downstream hanger assembly.
Upstream hanger assembly removal
Figure 9-7:
9.4
Mechanical assembly
Protect the rotor blades from rough handling as blade position is critical to turbine meter
performance.
Planned maintenance
76
Daniel Series 1500 Liquid Turbine Meter, NPS 3-24
Summary of Contents for daniel 1500 series
Page 8: ......
Page 12: ...Plan 2 Daniel Series 1500 Liquid Turbine Meter NPS 3 24 ...
Page 64: ...Prepare the turbine meter for use 54 Daniel Series 1500 Liquid Turbine Meter NPS 3 24 ...
Page 66: ...Install 56 Daniel Series 1500 Liquid Turbine Meter NPS 3 24 ...
Page 72: ...Installation procedure 62 Daniel Series 1500 Liquid Turbine Meter NPS 3 24 ...
Page 74: ...Testing 64 Daniel Series 1500 Liquid Turbine Meter NPS 3 24 ...
Page 75: ...Part III Operate Operate User manual 65 ...
Page 76: ...Operate 66 Daniel Series 1500 Liquid Turbine Meter NPS 3 24 ...
Page 80: ...Maintain 70 Daniel Series 1500 Liquid Turbine Meter NPS 3 24 ...
Page 101: ...Decommission the turbine meter User manual 91 ...
Page 102: ...Decommission the turbine meter 92 Daniel Series 1500 Liquid Turbine Meter NPS 3 24 ...
Page 103: ...Decommission the turbine meter User manual 93 ...