Anchor and Load Requirements of Seismic Installation
91
Liebert
®
CW
™
System Design Manual
Figure A-7 Downflow plenum seismic mounting data, CW026 – CW114
Model Number
Clips Required
Approximate Location, in. (mm)
End
Front/Rear
Total
A
B
C
D
CW026, CW038, CW041
2
2
8
7.4 (188)
31.2 (792)
6.5 (165)
19.0 (483)
CW051, CW060
3
10
27.6 (701)
CW076, CW084
4
12
27.6 (701)
CW106, CW114
34.4 (874)
PLENUM HOLD-DOWN CLIP DIMENSIONS
PLENUM HOLD-DOWN CLIP DETAIL
(FRONT PANEL REMOVED FOR CLARITY)
INTERMEDIATE SUPPORT
PANEL(S) PROVIDED ON
IBC CERTIFIED TOP DUCT
COLLAR PLENUMS ONLY
(CW051 AND LARGER)
NOTE: FLANGES PROVIDED
ON BLOWER(S) OULET FOR
SUPPLY AIR DUCTING WHEN
SOLID PANEL PLENUM IS USED.
#8 SELF DRILLING
SCREWS THROUGH
CLIP, UNIT DUCT
COLLAR AND PLENUM
PANEL FLANGE
(TYPICAL ALL LOCATIONS)
1/4" SELF DRILLING
SCREWS THROUGH
CLIP INTO UNIT TOP
(TYPICAL FRONT/REAR)
END CLIPS
REAR CLIPS
FRONT CLIPS
A
B
B
B
ALL CLIPS AND FASTENERS ARE REQUIRED TO MAINTAIN IBC CERTIFICATION OF CONFORMITY
D
C
DPN003209
Pg. 5 Rev. 2
Summary of Contents for CW089
Page 2: ......
Page 8: ...Liebert CW System Design Manual vi ...
Page 10: ...Liebert CW System Design Manual vi Page intentionally left blank ...
Page 18: ...Nomenclature and Components Liebert CW System Design Manual 8 Page intentionally left blank ...
Page 62: ...Dimensions Liebert CW System Design Manual 52 Page intentionally left blank ...
Page 76: ...Piping Liebert CW System Design Manual 66 Page intentionally left blank ...
Page 90: ...Electrical Field Connections Liebert CW System Design Manual 80 Page intentionally left blank ...