1
Wireless planning
1.1
Power up sequence
The gateway should be installed and functioning properly before power
modules are installed in any wireless field devices. Wireless field devices
should also be powered up in order of proximity from the gateway
beginning with the closest. This will result in a simpler and faster network
installation.
1.2
Gateway redundancy
If the wireless gateway was ordered with redundancy (Gateway Redundancy
code RD), refer to Appendix D in the Emerson Wireless 1420 Gateway
for additional installation instructions.
1.3
Gateway firmware compatability
The gateway firmware needs to be compatible with host connections being
made. Verify that gateway firmware and host firmware (e.g. Security Setup
Utility (SSU) and Plantweb Insight) are compatible before commissioning.
July 2022
Quick Start Guide
Quick Start Guide
5
Summary of Contents for 1410S
Page 1: ...Quick Start Guide 00825 0600 4410 Rev BB July 2022 Emerson Wireless 1410S Gateway ...
Page 4: ...Quick Start Guide July 2022 4 Emerson com ...
Page 19: ...Figure 4 1 Emerson 1410S1 Mounting July 2022 Quick Start Guide Quick Start Guide 19 ...
Page 38: ...7 2 8 Declaration of Conformity Quick Start Guide July 2022 38 Emerson com ...
Page 39: ...July 2022 Quick Start Guide Quick Start Guide 39 ...
Page 40: ...Quick Start Guide July 2022 40 Emerson com ...
Page 41: ...July 2022 Quick Start Guide Quick Start Guide 41 ...
Page 42: ...Quick Start Guide July 2022 42 Emerson com ...
Page 43: ...July 2022 Quick Start Guide Quick Start Guide 43 ...