Quick guide for TBA firmware V1.070
5. Starting the tester in the “5h, 10h, 20h Discharge” mode.
If a battery with a rated voltage is attached to the tester:
for TBA 60 (48/110/220) – 48V, 110 V or 220V,
for TBA 150 (24/48/80) – 24V, 48V or 80V,
for TBA 150 (6/12/24) – 6V, 12V or 24V,
the following modes can be selected by means of the [F2] button
(figure 13)
:
•
5h Discharge Current – determining battery efficiency according
to Q5
•
10h Discharge Current – determining battery efficiency according
to Q10
•
20h Discharge Current – determining battery efficiency according
to Q20
To proceed to the next screen choose „Next” by pressing the button
[F3].
Discharge parameters setting
(figure 14)
:
Using the [F2] button and the adjuster set:
- value of rated capacity of the tested battery „Qn”,
- the final voltage of the discharged cell „Vk”,
- in the case of the TBA 60 tester set the correct number of tested
cells (this parameter is unavailable in the TBA 150 testers).
To proceed to the next screen choose „Next” by pressing the button
[F3].
Data logging screen.
(figure 15)
Using the [F2] button place the cursor on Data logging and by means
of the adjuster choose the number of memory bank where the data
will be recorded during the battery test. You can select only empty
banks which protects against erasure of data from previous recordings.
In order to avoid recording set No.
Using the [F2] button place the cursor on Period and set the period
of data recording by means of the adjuster.
The change of the data recording period implies the change of the
Time of Data Recording whose value is displayed.
Deleting and saving of the banks is described in point 5 of the manual.
To proceed to the next screen choose „Next” by pressing the button
[F3].
Discharge home screen.
(figure 16)
After pressing the (green) [ON] button the discharge current will flow,
and the fans which cool the tester heaters will start working.