Ensure that the correct cable and gland are at hand.
•
Be sure to allow enough length stripped cable.
•
Pass the cable through the cable gland and ensure that the cable is
correctly positioned in the gland. Eltorque recommends having a 5mm
cable edge over the end of the gland.
•
Hold the body of the gland in position with a spanner (24mm / 0.94 in.)
or wrench to prevent rotation and tighten the back-nut to min 5Nm,
maximum 15Nm.
•
Finalize the gland installation with a visual verification to ensure correct
positioning of all parts.
•
For other glands follow the instructions from the supplier.
Figure 26: Mounting of cable gland
Note!
The connection of the power supply is identical for all types of
communication interface boxes for QT-series actuators.
Figure 27 shows the location of the terminal X4 with a pinout for incoming
and outgoing power cables. Each actuator has a double power supply
connector enabling serial powering of multiple actuators.
Verify that the voltage levels are following the product's requirements.
All terminals can accommodate:
Strip the wire-end to 9-10 mm (0.35in
–
0.39in).
•
Fine-stranded conductor
0.25 - 2.5 mm²/0.0098
–
0.0984 in
2
.
If ferrules are used the sole responsibility for a correct installation lies on the