10 BLADE LOUVRE
The louvre must be fitted to either side (excluding corner bays)
Procedure
1. Place top cill into position on side jamb of
louvre and secure with self tapping screws.
2. Do same on the other top corner.
3. Do same with bottom cill.
4. Please note that the handle is on the right
hand side.
To fit the louvre to the greenhouse frame;
The louvre MUST be sandwiched between 2
pieces of glass. It cannot sit directly on top of the
bottom cill.
The louvre is fitted from inside the greenhouse,
and you must ensure that the handles are on the
right (viewed from inside).
1.
Decide which bay you intend to fit to, and fit 1 piece of glass on the bottom cill (either ref T6
or T5 depending upon the required louvre height).
2.
Offer the louvre to the bay you intend to fit to and sit on top of the previously installed pane
of glass.
3.
Using the previously inserted bolts (or using 1/2 head bolts supplied) loosely fit the 4 brackets
as shown to the greenhouse frame, and then tighten so as to clamp the louvre frame to the
greenhouse.
4.
Fit remaining piece of glass above the louvre
Summary of Contents for 7'5" WIDE TITAN
Page 1: ......
Page 2: ......
Page 3: ......
Page 9: ...WELL DONE YOU HAVE SUCCESSFULLY COMPLETED THE 2 SIDE FRAMES ...
Page 11: ...REAR END ASSEMBLY ...
Page 16: ...DOOR END ASSEMBLY ...
Page 32: ...ELITE 1806 ...