Installation
SW 5250A•SW 3500A•SW 1750A
2-12 Operation
Manual
2.8.1
2.8.2
187 to 264 VRMS L–L 3-Phase Operation (3-Wire USA)
Connect the input wires to the phase A (F1), B (F2), and C (F3) input fuse terminals
(no Neutral is required).
Ensure that the chassis safety ground is also connected.
Use cables with ratings equal to or greater than the current rating listed on the unit or in
Table 2–7. Any phase sequence of wiring can be used.
342 to 457 VRMS L–L 3-Phase Operation (4-Wire INTL)
It is essential that the Neutral connection is present when using the unit. An external
circuit breaker is required for the 3-phase voltages.
Do not pass Neutral through the
breaker.
Only units that are factory set at this voltage will operate at this voltage.
CAUTION!
Neutral must not be broken by an external switch. Severe damage to
the unit may occur if Neutral is broken and phase voltage is present.
Connect the input wires to phases A (F1), B (F2), C (F3) and Neutral.
Ensure that the
chassis safety ground is also connected.
Use cables with ratings equal to or greater
than the current rating listed on the unit or in Table 2–7.
2.8.3 Single-Phase
Input Connections
The SW system is designed for three-phase input power operation, either 3-wire (USA)
or 4-wire (EUR) plus a chassis safety ground. However, if only single-phase input
power is available, the configurations listed in Table 2–8 are possible.
An overcurrent protection device and a device for disconnecting the single-phase
energy supply source are required as indicated in Section 2.8 above.
Summary of Contents for SmartWave SW1750A
Page 2: ... ...
Page 4: ...Committed to Quality Striving for Excellence ii ...
Page 5: ...This page intentionally left blank iii ...
Page 8: ......
Page 31: ...SW 5250A SW 3500A SW 1750A Installation Operation Manual 2 5 Figure 2 3 SmartWave Rear Panel ...
Page 66: ...Operation SW 5250A SW 3500A SW 1750A 3 22 Operation Manual Table 3 1 Sequence Execute Menu ...
Page 90: ......