7.2 Leak Check Gas Piping
Pressure test boiler and gas connection before placing
boiler in operation.
• Pressure test over 1/2 psig (3.5 kPa). Disconnect
boiler and its individual gas shutoff valve from
gas supply system.
• Pressure test at 1/2 psig (3.5 kPa) or less.
Isolate boiler from gas supply system by closing
manual gas shutoff valve.
• Locate leakage using gas detector, noncorrosive
detection fluid, or other leak detection method
acceptable to authority having jurisdiction. Do
not use matches, candles, open flames, or other
methods that can provide ignition source.
• Correct leaks immediately and retest.
NOTICE
Sediment trap shall be located upstream of gas
controls.
7 - GAS SUPPLY & PIPING
FIGURE 7-1 GAS LINE CONNECTION WITH MANUAL MAIN
SHUTOFF VALVE WITH UNION AND SEDIMENT TRAP
Illustration shown (GMCB150)
Supplied external manual
main gas shutoff valve
(shown in open position)
with field supplied union, and
sediment trap