![EcoFasten Clickfit Installation Manual Download Page 19](http://html1.mh-extra.com/html/ecofasten/clickfit/clickfit_installation-manual_2354081019.webp)
VERSION: v3.0
REVISION DATE: 12/2/22
INSTALLATION GUIDE
GROUNDING
PAGE
18
BONDING PATHS
Bonding paths are carried throughout the array in a variety of ways. They are carried module-to-
module and module-to-rail through mid clamps, carried at rail-to-rail connections through the
splices, and carried row-to-row using module jumpers or grounding lugs with bare copper. For
easy row to row bonding, EcoFasten recommends using our Module jumper.
BONDING AND GROUNDING
MODULE JUMPER
1 module jumper
bonding module to
module and row to row
MID CLAMP
2 mid clamps bonding
pairs of modules
GROUNDING LUG
1 ground lug per
continuous array
RAIL SPLICE
1 splice bonding
adjacent pair of rails