Automatic Transfer Switch - VERSO 200 - Quick Commissioning Guide 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

This equipment must only be installed by qualified 

electrical personnel. 

 

Maintenance operations and configuration of this 

equipment must be carried out by authorised and 

trained personnel. 

 

Once installed and switched on this equipment 

may be powered by two different voltage sources. 

These two voltage sources are dangerous and are 

capable of causing harm to the human body. 

 

 

For more information consult the user manual. 

 

 

Safety Instructions 

         

  

 

Temperature: -10°C to +40°C (without derating) 

Temperature: -20°C to +70°C (with derating) 

 

Storage: -20°C to +70°C 

(Maximum duration one year) 

 

 

Altitude: 2000m max. without derating 

 

Humidity: 80% without condensation, up to 55°C 

 

 

   95% with condensation, up to 40°C 

 

Level of protection: IP2x from 200A to 630A 

                                    IP55 from 800A to 3200A 

Weight: sizes 200A - 630A, from 35kg to 40kg 

               sizes 800A - 1600A, from 200kg to 250kg 

               sizes 1600A - 3200A, from 415kg to 450kg 

 

 

 

Environmental conditions 

           

 

 

Check the data plate to ensure that the size of the switch and the range of voltage are suitable for the 

required application (e.g. 200A, 380VAC to 440VAC). 

 

Ensure that suitable electrical protection (circuit breaker or fuse) is connected upstream of the switch (This 

applies to both the mains side and the generating set side). 

 

Read carefully the information provided on the electrical drawing. 

 

 

 

Preliminary checks 

 

 

 

The electrical box has four 7mm diameter holes for wall mounting or affixing to a suitable metallic bracket. 

Only use suitable professional materials for the mounting bracket.   

The template for mounting the box is shown on the packaging. 

 

The box must be positioned vertically, as shown in the picture opposite. Power connections 

are provided through the bottom of the box, regardless of size. 

 

  

Mounting and Installation 

 

 

 

Use cables of appropriate length and gauge  for the size of the switch  taking into account the distance 

between the switch and: 

. Mains circuit breaker S,  

. Genset circuit breaker M

. Users load O

 

The table opposite shows typical cable gauges used: 

Important: The table does not take into account voltage drops in the 

cables (caused by distance and methods of installation). 

 

The non-magnetic cable gland plate at the bottom of the transfer 

switch is designed to accommodate cable glands with mechanical 

latching. 

 

After preparing the cable ends using suitable lugs, connect them to the connection points on the switch 

or to the copper busbars while respecting the tightening torque.  

Each cable link must have a protective conductor connected to the 

enclosure using the available welded studs. 

 

 

 

Power Connections 

 

 

 

 

 

 

 

(*) Warning, risk of electric shock 

 

Summary of Contents for VERSO200

Page 1: ... et de fonctionnement Operating instruction manual Manual descriptivo y de funcionamiento SDMO Inverseur de sources automatique Automatic transfer switch Inversor de fuentes automático VERSO200 02 08 2013 33514066401_0_1 ...

Page 2: ... switch This applies to both the mains side and the generating set side Read carefully the information provided on the electrical drawing Preliminary checks 3 The electrical box has four 7mm diameter holes for wall mounting or affixing to a suitable metallic bracket Only use suitable professional materials for the mounting bracket The template for mounting the box is shown on the packaging The box...

Page 3: ...monitoring fault source 1 4 Source 2 switch open Source 2 switch closed Position monitoring fault source 2 5 No force switch to source 1 Force switch to source 1 selected 6 No force switch to source 2 Force switch to source 2 selected 7 AUTO mode not selected AUTO mode selected 8 TEST mode not selected TEST mode selected Diagnostics LED functions 8 4 key navigation keypad 9 Access to previous menu...

Page 4: ... genset circuit breaker check voltage and phase sequence If phase rotation is not correct LED 12 turns red open the genset breaker and restore phase sequence Commissioning 10 Source 1 present and parameters are correct Frequency source 2 Voltages phase to neutral of type 3P N Phase voltage between phases of type 3P N Electrical measurements display 11 Displays may be different depending on type of...

Page 5: ...on at source 1 2 AUTOSET OK auto configuration initialising MODE EJP EJP STOR mode engaged France only AUTOSET auto configuration in progress flashing PROGRAM Program inprogress DEL test switchedon On the third and fourth lines the following action messages may be displayed T00 003s 1 0 Transfer Timer 1 OK CONFIRM _____CONFIRM OK Manual confirmation of return to mains T01 005s 2 1 Return to mains ...

Page 6: ...ers A11 N function Range of adjustment Standard range N function Range of adjustment Std settings T00 Loss of source 1 0s to 180s 3 T26 Screen scrolling time 1s to 10s 5 T01 Return source 2 0s to 999s 5 T27 Automatic configuration 0s to 999s 3 T02 min U source 1 0s to 999s 5 T28 Min critical U source 1 0s to 999s 1 T03 max U source 1 0s to 999s 5 T29 Max critical U source 1 0s to 999s 1 T04 min U ...

Page 7: ...ening of source 2 F06 2 OK source 2 OK F10 IN 1 Input 1 reporting F03 1 Closure of source 1 F07 AUTO NOK mode AUTO not OK F11 IN 2 Input 2 reporting F04 2 Closure of source 2 F08 2 T22 Request load shedding F12 IN 3 Input 3 reporting Programming inputs and outputs 1 Press OK 2 Press until you reach menu I O 3 Press OK 4 In the Input Output menu press or until you reach the desired input IN 1 IN 2 ...