Per NEC article 300, 3(B)(1), all three-phase conductors must be run in the same conduit.
Conduit is sized to accommodate one neutral conductor the same size as the phase conductor and one ground
conductor sized in accordance with NEC Table 250.122.
Conduit sizes listed are for copper wiring only.
Table 23. 600V Power Cable Conduit Recommendations
UPS Model
Voltage
Terminal
Number of
Wires in
Conduit
Minimum
Conduit
Trade Size
Number of
Conduits
Eaton 9395P-600/550
600 Vac
AC Input to UPS Rectifier
(A, B, C, Ground)
4
3
4
AC Input to Bypass and Output
(A, B, C, Ground)
4
3
3
Eaton 9395P-600/500
600 Vac
AC Input to UPS Rectifier
(A, B, C, Ground)
4
3
4
AC Input to Bypass and Output
(A, B, C, Ground)
4
3
3
Eaton 9395P-600/450
600 Vac
AC Input to UPS Rectifier
(A, B, C, Ground)
4
3
3
AC Input to Bypass and Output
(A, B, C, Ground)
4
3
3
Eaton 9395P-600/400
600 Vac
AC Input to UPS Rectifier
(A, B, C, Ground)
4
3
3
AC Input to Bypass and Output
(A, B, C, Ground)
4
3
3
Eaton 9395P-600/300
600 Vac
AC Input to UPS Rectifier
(A, B, C, Ground)
4
3
2
AC Input to Bypass and Output
(A, B, C, Ground)
4
3
2
DC
(same for all ratings)
Battery
(Positive, Negative, Ground)
See Note 1
NOTE 1 Select conduit taking into consideration the DC input wire sizes and terminations listed in appropriate Tables, type of battery
installation, and requirements from NEC Table 4, Electrical Metallic Tubing (EMT).
NOTE 2 Bypass conduit data is not applicable to IOM configurations.
Battery Conductor Routing
: Refer to the notes at the bottom of
Input/Output Ratings and External Wiring Requirements.
Summary of Contents for Power Xpert 9395P-600/600