background image

Instruction Leaflet IL019107EN

Effective October 2015

Magnum DS

T

 switchgear terminal boots 

for cable connections—installation

m

 WARNING

(1) ONLY QUALIFIED ELECTRICAL PERSONNEL SHOULD 

BE PERMITTED TO WORK ON THE EQUIPMENT. 

 

(2) DO NOT ATTEMPT TO INSTALL OR PERFORM 

MAINTENANCE ON THE EQUIPMENT WHILE 

ENERGIZED.  ALWAYS VERIFY THAT NO VOLTAGE  

IS PRESENT BEFORE PROCEEDING. 

 

(3) ALWAYS DE-ENERGIZE PRIMARY AND SECONDARY 

CIRCUITS IF A CIRCUIT BREAKER CANNOT BE 

REMOVED TO A SAFE WORK LOCATION. 

 

(4) DRAWOUT CIRCUIT BREAKERS SHOULD BE LEVERED 

[RACKED] OUT TO THE DISCONNECT POSITION. 

 

FAILURE TO FOLLOW THESE STEPS FOR ALL 

PROCEDURES DESCRIBED IN THIS INSTRUCTION 

LEAFLET COULD RESULT IN DEATH, BODILY INJURY,  

OR PROPERTY DAMAGE.

General

Care should be exercised during installation to 

minimize cuts and gaps in the boot material for 

maximum coverage of the connection.

Required tools and supplies

• 

Heavy-duty box cutter knife or similar

• 

Plastic cable wire-ties

Parts provided

Each shipment shall contain one terminal boot per 

phase for each circuit. Boots vary in size based on 

the number of lugs/cables per terminal adapter. 

The illustrations herein represent only one size, 

but all items are installed in like manner.

Installation of insulated  

terminal boots

Step 1

As shown in 

Figure 1

, open the “clam-shell” 

shaped boot with the “hinge” area away from the 

cable path. Flex and install the boot so that the 

opening in the boot will surround the conductor 

between the glass-polyester conductor support 

and the cables. Orient the boot so that the 

terminal adapter copper bar will be encased inside.

Figure 1. Step 1

Reviews: