10
Installation
EATON ICUBE 2.0
UM.ICUBE2.0.SG.0822 August 2022 www.eaton.com
3 Installation
The system installation must be performed by an installer or field technician authorized
by Eaton
Eaton iCube 2.0 installation diagram is as follows (marked “*” applicable to Row cabinets system and split
cooling system)
Unpacking, Handling
Check monitoring&control system
*Joining the cabinets
Start-up and commissioning
Proceed with battery installation
Installation inspection
* Cooling outdoor unit installation
Input wiring connection
3.1 Joining the cabinets
Eaton iCube 2.0 cabinets are easy to combine. The main steps applicable to row (multiple) cabinets
are as follows:
•
Remove the side panel of the main equipment cabinet and side panel of IT cabinets
•
Remove the side panel fixing screws and side panel fixing accessories.
•
Loosen the sliding bolt screws of the side panel and slide them to prevent them from jamming the
cabinet body;
•
Remove the ground cable between the side panel and the cabinet body
•
Lift up the side plate and remove it by moving it.
•
Joining the cabinets
•
Place the main cabinet and sub cabinets in order according to the number marked on the lower right of the
front door of the cabinet.
•
Secure and fix adjacent cabinets with cabinet screws and rivets (6 pcs per each adjacent cabinet).
•
Connect the ground wire pairs of two adjacent cabinets
•
Install the top cable tray
•
Install the side door, removed in step 1, on the end cabinet
Installation