44
Eaton 93PM Integrated Battery Cabinet-Small Welded (IBC-SW) Installation Manual 164000639—Rev 03
requirements. Refer to the applicable Eaton 93PM UPS Installation and Operation manual listed in
paragraph
, for UPS cabinet terminal locations.
6.
Proceed to
Step 10
.
7.
Bottom Entry Wiring.
Remove the bottom conduit plate (see
) from the inside bottom of the
IBC–SW. Identify all conduit requirements and mark their location. Drill and punch all conduit holes in the
bottom conduit plate prior to mounting on the IBC–SW. Install the conduit plate and install all conduit runs
into the plate. Pull the wiring through the conduit into the wiring areas.
NOTE
In multiple IBC–SW installations, route the battery interface wiring between IBC–SWs
through the top of the adjacent IBC–SW using the top side inter-cabinet access pass-
through (see
).
8.
Route the thermal sensor interface wiring from the UPS thermal sensor (building alarm) interface terminals
through the bottom of the IBC–SW to the wiring channel on the left side of the IBC–SW (see
Route the wiring along the wiring channel to the IBC–SW battery interface terminal block TB2. See
for terminal locations. See paragraph
IBC–SW Interface Wiring Preparation
, and
for wiring and termination requirements. Refer to the applicable Eaton 93PM UPS Installation
and Operation manual listed in paragraph
, for UPS cabinet terminal locations.
9.
Secure the interface wiring to the wire tie anchors (see
) using Zip ties.
10. Connect the thermal sensor interface wiring to the IBC–SW thermal sensor interface terminals. See
paragraph
IBC–SW Interface Wiring Preparation
and
for termination requirements.
For a detailed view of the IBC–SW terminal block, see
.
11. Connect the thermal sensor interface wiring to the UPS thermal sensor interface (building alarm) terminals.
Refer to the applicable Eaton 93PM UPS Installation and Operation manual listed in paragraph
, for UPS cabinet termination requirements.
NOTE
In the following step, if the safety shield cannot be reinstalled because of misalignment,
use the leveling feet to realign the cabinet.
12. Reinstall the internal safety shield panel removed in
Step 3
of paragraph
Line-Up-and-Match Power Wiring
13. Install the front cover (previously removed) by carefully lowering the cover onto the bottom mounting
bolts. Secure the top of the cover with the two retained mounting bolts and tighten the bottom bolts.
14. Once the battery cabinets are installed and wired, return to the applicable Eaton 93PM UPS Installation and
Operation manual, listed in paragraph
, to complete the UPS wiring.
44..55
IInniittiiaall S
Sttaarrttuupp
Startup and operational checks must be performed by an authorized Eaton Customer Service Engineer, or the
warranty terms specified in
become void. This service is offered as part of the sales
contract for the UPS. Contact an Eaton service representative in advance (a minimum two-week notice is
required) to reserve a preferred startup date.
44..66
C
Coom
mpplleettiinngg tthhee IInnssttaallllaattiioonn C
Chheecckklliisstt
The final step in installing the IBC–SW is completing the following Installation Checklist. This checklist ensures
that you have completely installed all hardware, cables, and other equipment. Complete all items listed on the
checklist to ensure a smooth installation. Make a copy of the Installation Checklist before filling it out, and
retain the original.
After the installation is complete, an Eaton Customer Service Engineer must verify the operation of the UPS
system and commission it to support the critical load. The service representative cannot perform any
Summary of Contents for IBC-SW
Page 68: ...16400063903 164000639 03...