Commissioning
Switching on
Before startup check whether the power supply, inputs,
outputs, the serial interface and the EZ-NET connection are
properly connected:
• 24 V DC version:
– Te24 V: +24 V voltage
– Terminal 0 V: 0 V voltage
– Terminals I1 to I12, R1 to R12:
Actuation via +24 V
• 230 V AC version
– Terminal L: Phase conductor L
– Terminal N: Neutral conductor N
– Terminals R1 to R12:
Actuation via phase conductor L
If you have already integrated devices into a system, secure
any parts of the system connected to the working area to
prevent access and ensure that no-one can be injured if, for
example, motors start up unexpectedly.
Setting the menu language
When you switch on EZD for the first time, you will be asked
to select the menu language.
X
Use the cursor buttons
Í
or
Ú
to select the language
required.
– English
– German
– French
– Spanish
– Italian
– Portuguese
– Dutch
– Swedish
– Polish
– Turkish
ENGLISH
å
DEUTSCH
FRANCAIS
ESPANOL