External Acknowledgments
Within the [Ex Acknowledge] menu, the User can assign a signal (e.g.: the state of a digital input) from the assignment
list that:
•
Acknowledges all (acknowledgeable) LEDs at once;
•
Acknowledges all (acknowledgeable) Output Relays at once; or
•
Acknowledges all (acknowledgeable) SCADA signals at once.
Within the [Protection Para\Global Prot Para\TripControl] menu, the User can assign a signal that acknowledges a
pending trip command.
For details, please refer to the Trip Control
section.
External Acknowledge Via PowerPort-E
•
If PowerPort-E is not running, please start the application.
•
If device data have not been downloaded recently, select »Receive Data From The Device« from the »Device« menu.
•
Double click on the »Device Parameter« icon in the navigation tree.
•
Double click on the
»Ex Acknowledge« icon within the operation menu.
•
In the working window, the User can now assign each signal that resets all acknowledgeable LEDs, a signal that
resets all Relay Outputs, a signal that resets the SCADA signals respectively, and a signal that acknowledges a
pending trip command.
www.eaton.com
238
1..n, Assignment List
Ack LED
1..n, Assignment List
Ack RO
1..n, Assignment List
Ack Comm
Ex Acknowledge.Ack LED
Ex Acknowledge.Ack RO
Ex Acknowledge.Ack Comm