4.
Reconnect truck control/power harness (see
Figure 9
).
•
Plug the nine fiber optic cables labeled A+, A-, B+, B-, C+, C-, TA,
TB & TC in the correctly marked ports on the truck fanout boards.
(Standing in front of the structure, left-to-right is phase-A, phase-
B, phase-C respectively.)
•
Reconnect the 48V power supply wires to the fanout board power
sockets on each pole.
•
Strap fiber and 48V power supply wire harness back down to the
truck using the hook & loop straps.
2.4 RVSS structure transport/lifting
For moving the AMPGARD RVSS structure, units are shipped on
fork truck pallets (see
Figure 17
). These allow easy transport to the
installation area where they may then be lifted off the pallets and
into place by use of overhead lifting angles.
Figure 17. Moving pallet with a forklift.
•
To remove from shipping pallet, locate and remove the lag bolts
holding all structures down to the shipping pallet (see
Figure 17
below and note A in
Figure 21
.)
Figure 18.