7.
Open the UPS input and bypass feeder circuit breakers.
8.
Open all external battery breakers.
7.3.10
Charge
r
control
To turn the battery charger on:
1.
Select the CONTROLS symbol in the main menu bar.
The System Control screen is displayed.
2.
Select Battery in the System Control screen.
3.
In the Battery System Control screen, select the RESTING
→
CHARGING command and press the
push button.
To turn the battery charger off:
1.
Select the CONTROLS symbol in the main menu bar.
The System Control screen is displayed.
2.
Select Battery in the System Control screen.
3.
In the Battery System Control screen, select the CHARGING
→
RESTING command and press the
push button.
7.3.11
Battery test
NOTE: This UPS has a user initiated battery test that is intended to
determine if the batteries are able to support the load.
The battery test can only be initiated when the battery is fully charged.
This normally occurs within 72 hours of the start of a charging cycle.
The command is not shown if the test cannot be run.
To start the battery test:
1.
Select the CONTROLS symbol in the main menu bar.
The System Control screen is displayed.
2.
Select Battery in the System Control screen.
3.
In the Battery System Control screen, select the RESTING
→
TESTING command and press the
push button.