22 Operation
Sealer Operation
Seal Time
Use the “Seal TIME” timer to set the seal time. The seal time is the amount of time that
the magnets will hold the seal head down on the film. The seal time may vary according
to the type of film in use.
When the seal bar frame is pressed down onto the film, it will
remain in position for the set time then automatically release. Do
not hold the seal bar down onto the film.
Ensure that the timer sliding switches are in the times one (X1)
and the second (Sec) positions. If the timing switches are in the
X10 and or the minute positions it will result in a ridiculous value
that is way out of operating range.
Attention!
Move the “Seal TIME” switch in very small
increments.
Take Away Time
Use the “Take-away TIME” to set the amount of time the conveyor will run.
When the seal bar is released the conveyor will automatically
move the product into the shrink tunnel according to the set time.
The take away time will vary according to the product being
sealed and the operator’s ability.
Ensure that the timer sliding switches are in the times ten (X10)
and the second (Sec) positions. If the timing switches are in the
X1 and or the minute positions it will result in a ridiculous value
that is way out of operating range.
Summary of Contents for L-Bar Sealer Tunnel Combo Unit Value Series
Page 1: ...VS1620 L Bar Sealer Tunnel Combo Unit Value Series User Guide ...
Page 2: ......
Page 4: ......
Page 7: ......
Page 36: ...36 Parts List ElectricalSchematic Sheet1of2 ...
Page 37: ...Parts List 37 ElectricalSchematic Sheet2of2 ...
Page 38: ...38 Parts List VS1620 L Sealer Tunnel Combo Unit MainAssembly ...
Page 48: ...48 Parts List HeatTunnelOuterJacket VS1620DC ...
Page 50: ...50 Parts List L SealerAndFrame VS1620E ...
Page 54: ...54 Parts List L SealerTakeawayConveyor LTS504B P ...
Page 61: ......
Page 62: ......