8.4.1
Location
Primary display is typically located on left instrument panel; secondary display is typically located
on right instrument panel. For specific location, see the
Equipment Installation Record
document
associated with the airplane.
8.4.2
Removal
1. Shut down airplane power.
2. Remove screws
that secure the SkyView HDX Display to instrument panel. Keep screws
for re-installation
.
3. Slide
SkyView HDX Display
out of instrument panel to expose backside of unit and gain
access to connectors.
4. Disconnect all cables and D37 and D9 electrical connectors from back of unit. This is
accomplished by removing two retention screws on both D37 and D9 electrical
connectors.
8.4.3
Installation
1. Connect D37 and D9 electrical connectors and all cables to back of unit.
2. Slide
SkyView HDX Display
back into instrument panel.
3. Reinstall screws that secure unit to instrument panel (see
if screws need to be replaced).
4. If all other removed system components are installed, reconnect battery and provide
power to
SkyView HDX Display
and other system components.
5. Make sure
SkyView HDX Display
powers up normally and no unexpected messages
appear. If an issue occurs, see Section