3.3.3 Floor protection
-
If the floor is made of non combustible
material, no floor protector is required.
-
If the floor is made of combustible
material, a floor protector is required
(see table below).
FLOOR PROTECTION*
CANADA
USA
A
18" (457 mm)
From door opening
16" (406 mm)
From door opening
B
N/A (USA only)
8" (203 mm)
From door opening
C
8" (203 mm)
N/A (Canada only)
D
8" (203 mm) – Note 1
N/A (Canada only)
E
N/A (USA only)
Note 2
*Steel with a minimum thickness of 0.015" (0.38 mm) or ceramic tiles sealed together with
grout. No protection is required if the unit is installed on a non-combustible floor (ex:
concrete).
Note 1: The floor protection at the back of the furnace is limited to the furnace’s required
clearance (A) if such clearance is smaller than 8" (203 mm).
Note 2: Only required under the horizontal section of the connector. Must exceed each
side of the connector pipe by at least 2" (51 mm).
Summary of Contents for HEATMAX II DF01001
Page 30: ...HeatMax II Furnace Installation and Operation Manual 30 ...
Page 64: ...HeatMax II Furnace Installation and Operation Manual 64 11 Exploded diagram and parts list ...
Page 65: ...HeatMax II Furnace Installation and Operation Manual 65 ...
Page 66: ...HeatMax II Furnace Installation and Operation Manual 66 ...
Page 67: ...HeatMax II Furnace Installation and Operation Manual 67 ...
Page 68: ...HeatMax II Furnace Installation and Operation Manual 68 ...
Page 74: ...HeatMax II Furnace Installation and Operation Manual 74 12 2 1 Technical data HeatMax II ...
Page 75: ...HeatMax II Furnace Installation and Operation Manual 75 ...