2.4.1 VSmart Module Connections
You must remove the Intrinsically Safe barrier panel to attach wiring.
VSmart power
must be off
while connecting wires! Connect the
probe
wires and cables according to the following chart (see Figure 2-9 VSmart
Module Connections).
Probe Wiring
Probe
Wire
Probe Cable
(Belden #88760, #8760 or Alpha #55371)
VSmart Module
“Device”
Terminal
Blue
Red
PWR (power)
Brown
Black
SIG (signal)
Black
Shield
GND (ground)
AST Probe Wiring
Probe
Wire
Probe Cable
(Belden #88760, #8760 or Alpha #55371)
VSmart Module
“Device”
Terminal
Red
Red
PWR (power)
White
Black
GND (ground)
Shield
Shield
GND (ground)
2.4.2 VSmart & I/O Module AC Wiring
1. Pull two AC power wires from the circuit breaker to each
module; you may
“daisy chain” the wires from module to
module, not to exceed the circuit-breaker rating (see Figure 2-9).
2. Connect the live and neutral power wires to the appropriate
terminals in each module.
3. Make sure the modules are set for the correct voltages (115 or
230 VAC). For
VSmart Modules
, check the decal near the
terminal block. For
I/O Modules
, check the “line voltage selector”
switch on the circuit board.
4.
Determine the grounding method. There are two versions of the
VSmart Module: one has a single-ground terminal; the other has
a second-ground terminal for the I.S. barrier.
All ground
connections must be done with 12 AWG wire.
5. Ideally, all AC power should be in the same phase for best
operation.
Figure 2-9 VSmart Module Connections
Summary of Contents for OPW SiteSentinel iSite
Page 15: ...Page 15 of 145 www opwglobal com Figure 2 4 Console Connectivity ...
Page 17: ...Page 17 of 145 www opwglobal com Figure 2 6 Wiring Connections ...
Page 22: ...Page 22 of 145 www opwglobal com Figure 2 11 Standard Twisted Pair Petro Net Installation ...
Page 25: ...Page 25 of 145 www opwglobal com Figure 2 14 Petro Net Over Ethernet Option ...
Page 33: ...Page 33 of 145 www opwglobal com ...
Page 34: ...Page 34 of 145 www opwglobal com Figure 4 1 924B Probe Installation ...
Page 61: ...Page 61 of 145 www opwglobal com Figure 5 22 In Tank Probe Setup ...
Page 74: ...Page 74 of 145 www opwglobal com Figure 9 3 Dry Well Monitoring Single Wall Tank ...
Page 78: ...Page 78 of 145 www opwglobal com Figure 9 7 Double Wall Tank with Well Monitoring ...
Page 90: ...Page 90 of 145 www opwglobal com Figure 13 7 ACR RIM Jumper Board ...
Page 142: ...Page 142 of 145 www opwglobal com Declaration of Conformity ...
Page 143: ...Page 143 of 145 www opwglobal com ...