8.3.6 Install the nozzle
Personnel:
Operator
+ additional qualification explosion pro-
tection
+ Additional qualification high pressure
Protective equipment:
Face protection
Protective workwear
Protective gloves
Requirements:
Removal of nozzle is complete.
Fig. 21: Install nozzle
1. Insert nozzle (2) into the air cap (1).
2. Push in air cap (1) with nozzle (2) into the
inlet for material supply (3).
3. Screw on cap nut (5) and tighten it.
4. Rotate screening (4) in clockwise direc-
tion into the required position.
ð
The air cap (1) is aligned.
Installation of nozzle is complete.
8.3.7 Remove packing seal.
The sealing collar consists of the following
components:
3x cap seal
3x O-ring
Personnel:
Operator
+ additional qualification explosion pro-
tection
+ Additional qualification high pressure
Protective equipment:
Face protection
Protective workwear
Protective gloves
Requirements:
The spray gun is locked.
Removal of nozzle is complete.
Removal of needle is complete.
Fig. 22: Remove sealing collar
1. Unscrew seal retainer screw (2) with
socket wrench SW 10mm.
2. Remove sealing ring (3).
3. Unscrew hexagonal nuts (1).
4. Pull out inlet for material supply (4)
towards the front.
ð
The hexagonal nut falls out.
5. Unscrew gland (6).
Maintenance
02/2020
EcoGun 2100 - MSG00004EN
26/52