Installation, Operation and Maintenance manual
14
Downflo
®
Evolution
INSTALLATION
All external equipment connected to the inlet, outlet or discharge
(e.g. ducting, rotary valve) should be correctly sealed. This can be achieved
by applying a continuous 5 mm bead of sealing compound to the mounting
surface, along each side of the hole pattern. For non-Donaldson Torit
equipment please also check supplier’s IOM manual for any specific
requirements.
Unloading and transport to location
Before unloading, remove all packing and strapping.
A crane is recommended for the unloading, transport and installation of the dust
collector.
Connect lifting sling to the lifting lugs with clevis pins and distribute loads
equally. Use spreader bar if necessary.
In case of inside installation, a vented dust collector will be provided with a special roof
flange. This allows the mounting of a blow off channel (max 3m) around the bursting
panel. Channel will divert escaping pressure outside the premises.
Ensure blow off channel is mounted on roof flange with the pre-drilled hole on the
same side as the sensor brackets of the bursting panel. This hole is used to pass the
cable of the sensor through the blow off channel.