background image

This manual contains specific precautions related to worker safety. The hazard alert image denotes safety 

related instructions and warnings in this manual. DO NOT install, operate, or perform maintenance on this 

collector until you have read and understood the instructions, precautions and warnings contained within this 

manual.

LP Panelized Baghouse 

684LP, 780LP and 882LP

Installation, Operation and 

Maintenance Manual

IOM AG8589301 (ENG)

Revision 1

English 

Master Language

Summary of Contents for 684LP

Page 1: ...nings in this manual DO NOT install operate or perform maintenance on this collector until you have read and understood the instructions precautions and warnings contained within this manual LP Paneli...

Page 2: ...operation and maintenance for the collector purchased Please read the manual before installing operating or performing maintenance on the collector as it contains specific precautions for worker safe...

Page 3: ...3 Hopper Assembly 23 4 Tangential Inlet Assembly 26 5 Bag Section Assembly 29 6 Clean Air Access Plenum Assembly 32 7 Clean Air Outlet Plenum and Roof Installation 34 8 Tubesheet Installation and Supp...

Page 4: ...ould comply with applicable codes and standards related to combustible dust Electrical installation must be performed by a qualified electrician This equipment is not designed to support site ducts pi...

Page 5: ...liability for the fitness of a mitigation strategy or product for a particular installation or application The process owner s final selection of dust collectors and risk mitigation strategies should...

Page 6: ...ntial inlet along with dust being constantly cleaned from the filter elements exits the LP system through the hopper and transition Access into the hopper and transition is also provided through the a...

Page 7: ...ately Standard explosion vents are intended for outdoor installations only Unless otherwise noted the explosion venting calculations are based on formulas from NFPA 68 for outdoor applications only wi...

Page 8: ...pany Inc LP Typical Components optional platform clean air plenum roof optional explosion vent transition hopper optional ladder tubesheet clean air outlet dirty air plenum tangential inlet legpack su...

Page 9: ...air outlet 3 Operation Typical Collector Start Up Shut Down Sequence Start Up 1 Start material discharge mechanism such as a rotary airlock if applicable 2 Start gear box motor for cleaning arm rotat...

Page 10: ...ation Note Some filters and the cleaning system components fan rotating arm and arm drive assembly are not shown for clarity dirty air inlet filter bags hopper flow straightener baffles tangential inl...

Page 11: ...nitor pressure drop across filters Abnormal changes in pressure drop may indicate a change in operating conditions and possibly a fault to be corrected 3 Monitor exhaust for any signs of material emis...

Page 12: ...F and lock out all power before performing service or maintenance work Do not operate with missing or damaged filters 1 Follow shut down sequence for the collector 2 Turn power OFF and lock out all po...

Page 13: ...oriented downward 10 Snap the bag in place with the tubesheet between the upper and lower rings on the filter bag collar See Filter Installation illustration 11 Slide the filter cage into the filter b...

Page 14: ...stalled and properly sealed Damper control not adjusted properly Check airflow in duct Adjust main system fan damper control until proper airflow is achieved and the blower motor s amp draw is within...

Page 15: ...r proper flow at product discharge flange on filter hopper Cleaning system Verify no debris or condensation in tube length running to gauge Check operation of LP reverse air cleaning fan Check operati...

Page 16: ...13 Donaldson Company Inc Appendix A Installation...

Page 17: ...position Foundation or support framing must be capable of supporting dead live wind seismic and other applicable loads Consult a qualified engineer for final selection of foundation or support framin...

Page 18: ...lifting points provided 4 Use clevis connectors not hooks on lifting slings 5 Use spreader bars to prevent damage to collector s casing 6 Check the Specification Control drawing for weight and dimens...

Page 19: ...Air Access Plenum Assembly assemble clean air exhaust plenum and roof section and set aside on a level surface 7 Clean Air Outlet Plenum and Roof Installation assemble roof together and onto clean ai...

Page 20: ...Lower Inlet UH Upper Hopper LH Lower Hopper T Transition A Material Discharge Mechanism Parts labeled in this illustration are for each ring of the collector and packaged in racks with a stamped meta...

Page 21: ...lt tight 4 Install all cross braces spanning the legs using the 3 4 in supplied hardware 5 Keep bolts partially tightened until the I beam perimeter frame can be set into place 6 Lay out the I beam fr...

Page 22: ...e sections are in place bolt the center plate in place 7 Install the center cap weldment with the center pipe inserted down through the cap plate center hole 8 Align and tighten all bolts 2 Tubesheet...

Page 23: ...ized Baghouse 684LP 882LP Tubesheet Assembly Items radial stiffeners quantity 6 center plate quantity 1 center cap quantity 1 tubesheet pie section inside and outside quantity 6 each curved stiffeners...

Page 24: ...connect curved stiffeners to radial stiffeners Tubesheet Connection Layout tubesheet center cap place after center plate is connected tubesheet center plate place after pie sections are in place and...

Page 25: ...22 LP Panelized Baghouse 684LP 882LP Tubesheet Upright Top Connecting Plate tubesheet center cap place after center plate is connected install these bolts when locating center cap...

Page 26: ...ther but still allow for some slippage Repeat steps until upper hopper assembly is complete 5 If there is a middle hopper assembly assemble it in the same way as the upper hopper assembly 6 After the...

Page 27: ...on hopper panels along with hopper transition to attach and guide during rotation Use caution when lifting rotating hopper Keep tension on all straps cables when lifting Failure to comply may result...

Page 28: ...four temporary lifting points and mounting hardware for use on other sub assemblies Note Lifting points Bolt On Usage use the provided bolt on lifting points and grade 5 hardware when moving panels in...

Page 29: ...flector plates can be installed for clockwise rotation shown or counter clockwise opposite of shown 4 Tighten deflector plate bolts 5 Lift the deflector section assembly from the tubesheet and set asi...

Page 30: ...the assembly from the tubesheet and set aside 9 Place the tangential inlet body panels which form the middle ring of the inlet onto the tubesheet using the tubesheet as a template Do NOT apply sealan...

Page 31: ...and bolt together 15 Install the Tubesheet Support Column Mount into the deflector section 16 Prepare the top flange of the hopper with sealant as shown 17 Use the provided lifting points on the defl...

Page 32: ...ing subassemblies together Align the outer bolt pattern of the dirty air plenum body panel with the corresponding pattern on the tubesheet Do not apply sealant between the dirty air plenum body panel...

Page 33: ...air plenum BS3 BS2 and BS1 6 Apply sealant to the top flange of each body panel ring See Detail B on Dirty Air Plenum Assembly illustration 7 Properly attach the lifting points with the Grade 5 hardwa...

Page 34: ...Sections Shown Detail A Vertical Seam Spacing Detail B Sealant Application sealant pattern bolt hole upper flange spaced by a minimum of 4 bolts vertical flange adjoining panels vertical flange see De...

Page 35: ...rive H Frame later in the installation sequence 2 Prior to setting an adjacent panel apply sealant to all external vertical flanges within 1 8 in from flange edge as shown 3 Press vertical flanges tog...

Page 36: ...ldson Company Inc Clean Air Access Plenum Assembly gusset sealant pattern upper flange bolt hole H frame mount panel first ring panel clean air access panel H frame mount panel Sealant Application doo...

Page 37: ...ilure 3 Press vertical flanges together align the holes and insert the 1 2 in bolt hardware Keep hardware hand tightened 4 Repeat steps 2 3 for each panel until the entire clean air outlet plenum ring...

Page 38: ...35 Donaldson Company Inc Roof Installation 12 ft Bag Clean Air Outlet Plenum Shown...

Page 39: ...an Air Plenum 12 ft Bag Clean Air Plenum Shown second ring clean air outlet plenum first ring clean air access plenum lifting lug with Grade 8 hardware panel with sprinkler coupling door frame at 90 r...

Page 40: ...he tubesheet center pipe using the provided 5 8 UNC x 6 threaded bolts The holes are slotted so that the tubesheet stiffeners will come to rest onto the column plate 2 Lift the tubesheet with the colu...

Page 41: ...the tubesheet and the elbow base 5 Lift the support channel H frame with seal box into clean air access plenum Align internal bearing with rotating elbow shaft and lower the H frame channel frame onto...

Page 42: ...me cleaning fan pillow block bearing and shim seal box urethane seal UHMW sweep shoe support channel frame H Frame Note grease the pillow block bearing during regular maintenance drive components rota...

Page 43: ...rive Chain Installation 11 Once rotating elbow shaft is correctly aligned tighten all mount bolts and bearing set screws 12 Install the drive chain on the sprocket as shown in the diagram below 13 Pre...

Page 44: ...tration 3 Lower the filter cage into the bag If the bag section is resting on the ground the cages will not drop seat completely at this time When the dirty air plenum is lifted into place the cages w...

Page 45: ...flange bolts and tighten 4 Install the Magnehelic Gauge which is provided with a mounting plate at a remote location suitable for observation Run two lines of the 1 4 in poly tubing provided from the...

Page 46: ...y Inc 30 o 60o Collector Assembly clean air plenum lifting lug detail Correct Axis Lift tangential inlet assembly bolt hole tangential inlet flange sealant application hopper assembly sealant pattern...

Page 47: ...dy panel flanges 4 Position the platform assembly Reinstall and tighten the existing hardware including the bolted connections for the platform railing and knee braces 5 Assemble the entire ladder sub...

Page 48: ...45 Donaldson Company Inc Platform Installation Ladder Installation platform platform assembly ladder assembly lower intermediate support if applicable intermediate support knee braces ladder...

Page 49: ...talling service Any wiring on the interior of the collector may need to be rated for explosive environments Consult your local codes 17 Fire Mitigation System Consult with local authorities when insta...

Page 50: ...he fan housings Do not look into fan outlet to determine rotation View the fan rotation through the back of the motor Check that the exhaust plenum is free of tools or debris before checking blower fa...

Page 51: ...7 Ensure the Magnehelic gauge is properly installed and functioning Refer to the included print for additional instruction 8 Ensure all collector access panels and doors are sealed and secure 9 Check...

Page 52: ...minant from collector as possible 2 Lock Out all energy sources 3 Remove all filters from the collector and dispose of in a suitable fashion for the dust in the collector See Filter Replacement for re...

Page 53: ...Dust __________________________________________________________________________________ Dust Properties Kst________________Pmax_______________ MIE_____________ MEC___________________ Accessories______...

Page 54: ...51 Donaldson Company Inc Service Notes Date Service Performed Notes...

Page 55: ...oducts manufactured by a third party Third Party Product may constitute contain be contained in incorporated into attached to or packaged together with the goods Buyer agrees that a Third Party Produc...