Assembling towers in the upright
User Information
Load-bearing tower Staxo 40
Assembling towers in the upright
Assembling towers in the upright with 'mounted-ahead' 1.20m frames
As a rule:
▪
In this erection method, the horizontal profile of the
Staxo 40 frame 1.20m must always be on top, to
ensure fall protection.
▪
Slide the diagonal cross onto the safety-catch bolt
and immediately secure it with the safety catch.
Installation example with Staxo 40 screw-jack foot
30cm and Staxo 40 4-way screw-jack head 30cm.
Erecting the first storey
➤
Insert screwjack base units.
➤
Connect the frames together with diagonal crosses.
➤
Insert Staxo 40 couplers.
Note:
If it is intended to crane-lift the tower, the frames must
all be linked in a crane-handling-safe manner by
Staxo
40 tube connectors D48.3mm. See also the sec-
tion entitled 'Lifting by crane'.
NOTICE
▪
Erect the load-bearing tower in the vertical
on ground that is statically capable of sup-
porting the load.
▪
If the load-bearing tower is over 6
m high,
back-stay it or combine it with other towers.
98024-207-02
98024-270-01
F
Diagonal cross
98024-267-01
98024-266-01
F
98024-213-02