General remarks
Original Operating Instructions
Platform SCP
Safety features
Rubber sheets or flaps for openings
of up to 50
mm in the decking
When planning the platforms, a gap to the wall or to the
next platform is allowed for to ensure there is enough
play for the lifting operation.
Closing the gap with a rubber sheet
Gap between two platforms
a ... 50
mm
Distance between bolted joints: approx. 20
cm
Gap between platform and wall
a ... 50
mm
Distance between bolted joints: approx. 20
cm
Closing the gap with a flap
Gap between two platforms
a ... 50
mm
Gap between platform and wall
a ... 50
mm
☞
Important note:
Cover these gaps to prevent any small items
from falling off.
A
Platform decking
B
Rubber sheet, 0.35x10.00m
C
Universal countersunk screw 5x50 + washer 6
A
Platform decking
B
Rubber sheet, 0.35x10.00m
C
Universal countersunk screw 5x50 + washer 6
98058-416-18
a
A
B
C
98058-416-17
a
A
B
C
A
Platform decking
B
Cover hinge SK 35cm
C
Universal countersunk screws
D
Raw sheet 3-S 31mm 300/150cm
A
Platform decking
B
Cover hinge SK 35cm
C
Universal countersunk screws
D
Raw sheet 3-S 31mm 300/150cm
☞
Important note:
The flaps must be open during the lifting opera-
tion.
98058-416-19
a
A
B
C
D
D
a
98058-416-20
A
B
C
D
Summary of Contents for Platform SCP
Page 2: ...2 999805802 03 2016 Original Operating Instructions Platform SCP ...
Page 3: ...Original Operating Instructions Platform SCP 3 999805802 03 2016 ...
Page 31: ...Original Operating Instructions Platform SCP Anchoring on the structure 31 999805802 03 2016 ...
Page 61: ...Original Operating Instructions Platform SCP Start up phases 61 999805802 03 2016 ...
Page 114: ...114 999805802 03 2016 Design variants Original Operating Instructions Platform SCP ...