Start-up phases – Lifting unit attached on one side
151
999805802 - 03/2016
2nd casting section
➤
Remove the service towers from the outsides.
➤
Apply concrete release agent and set up one side of
the formwork.
➤
Adjust the formwork.
➤
Mount the positioning-points.
➤
Mount the 'Boxes for latch'.
➤
Place the reinforcement.
➤
Close the formwork and tie it.
➤
Pour the 2nd section.
➤
Open the formwork.
➤
Clean the formwork.
98058-458-01
Summary of Contents for Platform SCP
Page 2: ...2 999805802 03 2016 Original Operating Instructions Platform SCP ...
Page 3: ...Original Operating Instructions Platform SCP 3 999805802 03 2016 ...
Page 31: ...Original Operating Instructions Platform SCP Anchoring on the structure 31 999805802 03 2016 ...
Page 61: ...Original Operating Instructions Platform SCP Start up phases 61 999805802 03 2016 ...
Page 114: ...114 999805802 03 2016 Design variants Original Operating Instructions Platform SCP ...