background image

 

 

 

© Central Heating New Zealand Ltd 

1 of 10 

July 2016 

DeLonghi i-KIR2 Commissioning Guide  

 

This document must be read in association with the i-KIR2 Installation Manual provided with the unit. 
It is essential the manual is read and followed to ensure the installation is per manufacturer’s 
criteria.  

The purpose of this document is to assist with the commissioning of the heat pump parameters and 
the connection of third party controls.  

Contents 

1. 

Pre-commissioning .......................................................................................................................... 1 

1.1. 

Pre-Commissioning Checks ..................................................................................................... 1 

1.2. 

Heat Pump Controller .............................................................................................................. 2 

2. 

System configuration ....................................................................................................................... 3 

2.1. 

System A: Heat Pumps controller used as room thermostat .................................................. 3 

2.2. 

System B: Heat pump switched on/off by room thermostat(s) .............................................. 4 

2.3. 

System C, A or B with a Hot Water Cylinder (DHW) ................................................................ 5 

2.4. 

Additional Settings & Information........................................................................................... 6 

2.5. 

Resetting Errors ....................................................................................................................... 6 

3. 

System Operational Checks ............................................................................................................. 7 

3.1. 

System A test procedure ......................................................................................................... 8 

3.2. 

System B test procedure ......................................................................................................... 9 

3.3. 

A or B with DHW test procedure ........................................................................................... 10 

 

 

1.

 

Pre-commissioning 

1.1.

 

Pre-Commissioning Checks 

 

Prior to Filling with water 

A)

 

Ensure the heat pump is installed in accordance with the installation manual.  

B)

 

Ensure the power is isolated to the unit 

C)

 

Remove the side cover of the unit to expose the water pump, compressor and electrical 
enclosure.  

D)

 

Check the pre-charge of the expansion vessel is set to 1 bar.  
 

Summary of Contents for i-KIR2

Page 1: ...guration 3 2 1 System A Heat Pumps controller used as room thermostat 3 2 2 System B Heat pump switched on off by room thermostat s 4 2 3 System C A or B with a Hot Water Cylinder DHW 5 2 4 Additional...

Page 2: ...ser level Press menu button for 3 seconds 2 For Install parameters hold down the 3 buttons together for 3 seconds 3 The parameter number 4 digits will be displayed and the value of the parameter 2 of...

Page 3: ...0 So that the controller turns the heat pump on and off according to the room set point on the controller set to 0 0 Room Set Point 1 Water Set Point 1 0 21 01 Flow temperature set point for heating 3...

Page 4: ...meter Description Value Default Set to 51 20 Terminal 20 21 ON OFF remote contact or EHS Alarm input 0 Disable Remote controller only 1 ON OFF remote contact 2 EHS Alarm input 0 1 21 01 Flow temperatu...

Page 5: ...to is controlled via a sensor in the hot water cylinder connected to the heat pump the sensor needs to be enabled Parameter Description Value Default Set to 51 07 Enable DHW sensor Terminal 7 8 0 disa...

Page 6: ...et Auto Power OFF and Manual See List of Error codes for the procedure to reset each error code Auto Automatically Once it returns to normal condition the error will be reset When the unit stops it ma...

Page 7: ...controller only which acts as a room thermostat B Standard central heating controller s to turn HP on and off heat pumps remote controller is not used as a room thermostat but still needed to set flo...

Page 8: ...pump will come on but will not go off in response to room temperature Test Turn on the heat pump with top left button if not on already and select heating sun symbol using heat cool button When the s...

Page 9: ...at pumps controller then the heat pump has been configured correctly Check the heating controls will turn the heat pump on and off If there is more than one thermostat turn them all off and then turn...

Page 10: ...n heating 2 Press the tap button briefly so the tap symbol appears on the screen 3 The DHW heat pump should turn on to heat the DHW provided the cylinder temperature is below the DHW set point minus t...